Loading...
2750 Sibley Memorial Hwy - Contractor's Material & Test CertificateContractor's Material and Test Certificate for Aboveground Piping PROCEDURE Upon completion of work, inspection and tests shall be made by the contractor's representative and witnessed by an owner's representative. All defects shall be corrected and system left in service before contractor's personnel finally leave the job. A certificate shall be filled out and signed by both representatives. Copies shall be prepared for approving authorities, owners, and contractor. It is understood the owner's representative's signature in no way prejudices any claim against contractor for faulty material, poor workmanship, or failure to comply with approving authority's requirements or local ordinances. Property name L,vS't S • -6 Cv Date ° 1 - R U Property address `` y / C �U�F , j 1t (."0( ia, ‘1 Plans LJ1 Accepted by approving authorities (names) ■ Address S Installation conforms to accepted plans Yes I 1 No Equipment used is approved g Yes I 1 No If no, explain deviations Instructions Has person In charge of fire equipment been instructed as Iii Yes I 1 No to location of control valves and care and maintenance of this new equipment? If no, explain Have copies of the following been left on the premises? Yes 1 1 No 1. System components instructions Yes 1 1 No 2. Care and maintenance instructions Yes 1 1 No 3:. N 'PA 25 Yes 1 _I No /� Location of system Supplies buildings Sprinklers Make Model Year of manufacture .. Orifice ' size Quantity Temperature rating & ?oI) ISS ok 1 �' PZAs' 511'1 '-1' ` a -- - -1I z. 011 x� In 1. �) Si? 'SS' i,5 " -,1430° c� '' RA ► `t J'1 - AA-60u,- i o s r � 1 e I 1 �'� z. 5 Pipe and fittings a ra Type of pipe .. ., r Type of fittings 1 w1 A Alarm vlae or flow indicator Alarm device Maximum time to operate through test connection type Make Model Minutes Seconds G .` 1 • .. C ( Di" "PS- 0 OA tOcx IL,s S•., :l.t, Sr,„os.. Dry pipe operating test -- iv Dr� Q. O. D. Make Model Serial no. Make Model Serial no. Time to trip through test connections Water pressure Air pressure Trip point air pressure Time water reached test outlet Alarm operated properly Minutes Seconds psi psi psi Minutes Seconds Yes No Without Q.O.D. 1 8 C� q Q _ act Ida X With Q.O.D. If no explain Hydraulic data nameplate Nameplate provided 1 Na If no, explain [5? Yes 1 Remarks Date left in service with all control valves open • Signatures Name of sprinkler contractor Tests witnessed by For property owner (signed) Title ` t' Date , For sprinkler contractgi' (signed) ..: _. Title Date — Additional explanations and notes Deluge and pon valves Operation I I Pneumatic 1 I Electric I I Hydraulic Piping supervised I I Yes I 1 No Detecting media supervised C] Yes I I No Does valve operate from the manual trip, remote, or both I I Yes 1 I No control stations? Is there an accessible facility In each circuit for testing? I IYes I INo If no, explain Make Model Does each circuit operate supervision loss alarm? Does each circuit operate valve release? Maximum time to operate release Yes No Yes No Minutes Seconds Pressure redwing valve test Location and floor Make and model Setting Static pressure Residual pressure (flowing) Flow rate Inlet (psi) Outlet (psi) Inlet (psi) Outlet (psi) Flow (gpm) Test description HydrOatatiC; Hydrostatic tests shall be made at not less than 200 psi (13.6 bar) for 2 hours or 50 psi (3.4 bar) above static pressure in excess of 150 psi (10.2 bar) for 2 hours. Differential dry - pipe valve clappers shall be left open during the test to prevent damage. All aboveground piping leakage shall be stopped. Pneumatic Establish 40 psi (2.7 bar) air pressure and measure drop, which shall not exceed 11/2 psi (0.1 bar) in 24 hours. Test pressure tanks at normal water level and air pressure and measure air pressure drop, which shall not exceed 11/2 psi (0.1 bar) in 24 hours. Tests All piping hydrostatically tested at C).- psi (.. bar) for hours If no, state reason .. Dry piping pneumatically tested J(1' Yes 1 1 No Equipment operates properly Yes I I No Do you certify as the sprinkler contractor that additives and corrosive chemicals, sodium silicate or derivatives of sodium silicate, brine, or other corrosive chemicals were not used for testing systems or stopping leaks? Yes I I No Drain test Reading of gauge located near water supply test connection: psi (, bar) Residual pressure with valve in test connection open wide: psi (____ bar) Underground mains and lead in connections to system risers flushed before connection to sprinkler piping Verified by copy of the U Form No. 85B 35 Yes 1 I No Flushed by installer of underground sprinkler piping I' Yes I 1 No made Other Explain If powder - driven fasteners are used in concrete, has I I Yes j ' No representative sample testing be satisfactorily completed? If no explain Blank testing gaskets Number used 0 Locations Number removed 0 Welding Welding piping > Yes I 1 No If yes.. . Do you certify as the sprinkler contractor that welding procedures comply isi Yes I I No with the requirements of at least AWS B2.1? Do you certify that the welding was performed by welders qualified in compliance with the requirements of at feast AWS B2.1? J i Yes I I No Do you certify that the welding was carried out in compliance with a documented quality control procedure to ensure that all discs are retrieved, that openings in piping are smooth, that slag and other welding residue are removed, and that w Yes I I No the internal diameters of piping are not penetrated? Cutouts (discs) Do you certify that you have a control feature to ensure that all cutouts (discs) are retrieved? Yes I I No