910 Lakewood Hills Rd - Inspection Remarks Report Name: City of Eagan Printed: 5/10/2014 Inspection Remarks Page: 1 Inspection Remarks Permit: EA114067 Permit Type: Building Site Address: 910 Lakewood Hills Rd 10/28/13 JTW footings - perimeter footings at the garage must be a min 24" wide and a min 10" deep - contractor was advised that an addendum has been submitted with revised foundation engineering and they will be responsible for any changes to the required reinforcing steel in the footing. 10/28/13 JTW footings Partial - OK to pour the front entry and garage perimeter footings only ( no other footings were ready) - provide a min 3" of cover on all reinforcing steel 10/31/13 JTW addendum - addendum approved to change the foundation to masonry, see revised engineering - addendum approved to change the vaulted roof frame at the master bdrm to I-joist see mfg specs - addendum approved to change the insulation in the ceiling below the garage to 2-1/4" spray foam insul + R-21 batts still need to verify the fastening of the suspended ceiling frame with the engineer 11/22/13 SP footings - 24x24 under stairs under pin ftg 11/22/13 SP Foundation - Changed to a partial inspection submit an addendum for the changes from the approved plan some foundation work not started yet JTW 02/12/14 JTW Framing - some footing and foundation not done yet STILL NEED TO DO FOOTINGS AND FOUNDATIONS - verify backfill inspection (no record) as per the foundation engineering 3/S 1 - partial framing inspection, roof and exterior wall framing of the existing house main floor and the master bedroom only contractor wants to poly the existing ceiling and spray foam the exterior walls of the existing house and spray foam the ceiling and exterior walls of the master bedroom to hold in some heat MASTER BEDROOM ADDITION OK ECPT BATH FAN HOOK UP Bath fan OK per Dale S 5/8/14 - plbg and Mech RI are not complete yet, elec RI is done STILL NEED TO HOOK UP BATH FAN AND HIGH VIS. SYSTEM AIR plbg in the master bdrm ceiling has been inspected OK TZ - add a dbI 2X10 header at the rear window as per the approved plan or submit an addendum - add PSL post as per the approved plan, supporting the new center beam at the existing house OK TZ - add bearing under the hand framed rafters and rafter supports where they land on the existing roof sheathing OK TZ - provide a full set of approved plans on site, including change to 16' 1-joists 19.2" OC for roof frame at the master bed room verify that rafter tail extentions are fastened as per the I-joist mfg spec OK TZ -add tie straps across the bottom of each ceiling joist at the center Beam see engineers detail on Page S 1 OK TZ - add blocking in the ceiling frame for a drag strut. see revised engineering detail on page S2 dated 8/26/13 - verify header over the pocket door (dbl 9-1/2" LVL) see revision dated 9/10/13 - (4) 2X4 bearing at the center bearing beam is required by the engineer (see 2/S1) any change ((3) 2X6) must be approved by the engineer - add fireblocking at the dbl wall between the mstr bdrm and the office OK per DS 5/8/14 - add ventilation shoots to the rafter spaces prior to insulation OK TZ - submit an addendum for ANY changes to the approved plan, to be reviewed prior to construction all approved addendums must be ATTACHED to the approved plan OK to poly the ceiling of the existing main floor, leave all corrections accessible*** OK to spray foam exterior walls of the main floor existing house and the master bedroom Only, leave all corrections accessible for inspection * * * OK to spray foam TJI rafter at the master bedroom AFTER ventilation shoots and rafter tail fastening is inspected*** 02/12/14 JTW sheathing e Report Name: City of Eagan Printed: 5/10/2014 Inspection Remarks Page: 2 Inspection Remarks Permit: EA114067 Permit Type: Building Site Address: 910 Lakewood Hills Rd - sheathing inspection not ready - remove house wrap at all designated braced wall panels and shearwalls for inspection (see engineering pages S 1 & S2) send correction to Bruce Schweich, B2 Design at bruce@b2designbuild.com 02/20/13 TZ Sheathing OK IN ALL AREAS EXCPT 7 FT ENGINEERED AREA BY KITCHEN OK TO COVER REST MUST TALK TO ENGINEER 2/20/13 TZ roof ice protection THEY WILL SEND JEFF PICS framing tz 4 9 14 see above list from jeff this is a list of items only they need to give jeff all of the addendums beam changes new holddowns engineering ect 1 add support under steel beam per engineers reports 2 fix hangers with more than 1/2 inch gap allowed OK TZ 3 vent bath fan in master bedroom DONE DS 4 nail spliced roof joists by fireplace 5 nail all hold downs they will need to submit all of the changes to the plans to Jeff and get a full approved set of plans on site see rem for list of items only 04/09/14 TZ Sheathing - they are adding straping that is different from the approved plans and engineering must bring new plans to Jeff 04/10/14 JTW Phone conversation with Bruce Schwiech - he will drop off revised plans for an addendum this morning and come back for a meeting Tommorrow morning I reminded him that all communication must go through the home owner that is the permit holder any changes that affect the existing engineering will need to be reviewed by the engineer of record he will provide documentation from Moleen, the span crete fabricator 04/10/14 TZ Mech RI 1 they need to install and vent boiler and water heater unit 2 they must show the high pressure forced air unit location in attic and how it will be installed and unit type 05/06/14 JTW - contractor dropped off revised plans at the counter 05/07/14 JTW - contractor came to the counter to discuss plans dropped off, have not been reviewed yet 05/08/14 DS - site visit 05/09/14 JTW there are several discrepancies between the revised plans, the approved plan & the engineering 05/09/14 JTW - contractor came to the counter to make changes on the approved plan 05/10/14 JTW - previous inspection remarks have been printed and added to the parcel file to make room for more comments Report Name: City of Eagan Printed: 5/10/2014 Inspection Remarks Page: 3 Inspection Remarks Permit: EA114067 Permit Type: Building Site Address: 910 Lakewood Hills Rd outstanding corrections and incomplete inspections will be restated below FOOTINGS - underpinning at the walk out wall not done yet FOUNDATION - provide an affidavit and any pictures that are available for foundation that was backfilled without inspection showing Each block core drained to an interior drain tile Exterior draintile Required water proofing Backfilled with sandy material as per engineering on 3/S 1 - under pinning of the walkout wall foundation as per the engineered detail to be provided - fastening of the precast to the foundation as per the precast mfg spec - core fill of existing foundation at 4 locations as per the engineering detail 1/S1 SHEATHING/BRACED WALLS - verify the 7 LF shear wall at the living room, done as per 5/S2 or submit an alt - provide an alt for two 4 LF interior gyp braced wall panels at the pantry powder room, laundry that were altered in the revised plans - adding a required sheetrock inspection for the required fastener pattern of the interior gyp braced wall panels (see S2) FRAMING - see corrections from Mech RI provide a detail for supporting the mech equip in the attic and the required access - verify repair of cut ceiling joists adjacent to the fireplace - provide full set of the most recent approved plan on site - verify that braced wall/ sheathing inspections have been completed Master bedroom walls and ceiling OK to insulate*** main floor existing construction OK to insulate EXCEPT corrections listed above*** Report Name: Inspection Remarks City of Eagan Printed: 5/10/2014 Page: 1 Inspection Remarks Permit: EA114067 Permit Type: Building Site Address: 910 Lakewood Hills Rd 05/10/14 JTW - previous inspection remarks have been printed and added to the parcel file to make room for more comments outstanding corrections and incomplete inspections will be restated below FOOTINGS - underpinning at the walk out wall not done yet FOUNDATION - provide an affidavit and any pictures that are available for foundation that was backfilled without inspection showing Each block core drained to an interior drain tile Exterior draintile Required water proofing Backfilled with sandy material as per engineering on 3/S1 - under pinning of the walkout wall foundation as per the engineered detail to be provided - fastening of the precast to the foundation as per the precast mfg spec - core fill of existing foundation at 4 locations as per the engineering detail 1/S1 SHEATHING/BRACED WALLS - verify the 7 LF shear wall at the living room, done as per 5/S2 or submit an alt - provide an alt for two 4 LF interior gyp braced wall panels at the pantry powder room, laundry that were altered in the revised plans - adding a required sheetrock inspection for the required fastener pattern of the interior gyp braced wall panels (see S2) FRAMING - see corrections from Mech RI provide a detail for supporting the mech equip in the attic and the required access - verify repair of cut ceiling joists adjacent to the fireplace - provide full set of the most recent approved plan on site - verify that braced wall/ sheathing inspections have been completed Master bedroom walls and ceiling OK to insulate*** main floor existing construction OK to insulate, leave corrections listed above accessible*** Lower level of the existing house and all of the new addition have not yet had a framing inspection ROOF ICE PROTECTION - provide pictures showing all of the roof ice protection prior to shingling