3950 Eagan Outlets Pkwy - Non Structural Steel Insp Report A Non-Structural Steel
Special Inspection Final Report
Cedar Grove Parking ramp
3950 Eagan Outlets Parkway
Eagan, Minnesota
Prepared for
City of Eagan
Project BL-12-04581A
August 13, 2Q14
Braun Intertec Corporation
' ' Braun Intertec Corporation Phone:952•995•z000
. iiooi Hampshire Avenue S Fax: 95z•995•2020
Minneapolis,MN 5543$ Web: braunintertec.com
August 13, 2014 Project BL-12-045781A
Mr. Russ Matthys
City of Eagan
3830 Pilot Knob Road
Eagan, MN 55122
Re: Non-Structural Steel Special Inspection Procedural and Final Report Submittal
Cedar Grove Parking Ramp
3950 Eagan Outlets Parkway
Eagan, Minnesota
Dear Mr. Matthys:
Please find attached to this procedural report the Non-Structural Steel Special Inspection Final Repart for
the above referenced project along with supporting Special Inspection Daily Reports for your review and
records.
Project Information
This project included the construction of a new parking ramp along the south side of Eagan Outlets
Parkway in Eagan, Minnesota.The ramp has two levels(one level above grade)with a footprint of about ,
272,000 square feet. The ramp is also designed and constructed to accommodate a third ievel addition in ,
the future.The ramp primarily has cast-in-place (CIP)and pre-cast cancrete columns and walls with post- '�
tensioned (PT) concrete decking. Some interior walls will also be concrete masonry unit (CMU) '�
construction.The south, east and west walls of the first level are designed as CIP retaining walls which ''�
retain soil masses and future construction behind them.The at grade level of the ramp has a ground I
supported CIP concrete slab. II
Special Inspection and Testing Procedures
The special inspection services were provided by International Code Council (ICC)certified special
inspectors in accordance with the requirements of Chapter 17 of the International Building Code (IBC),
the Special Inspection and Testing Schedule and/or the project plans and specifications.
The purpose of special inspections is to provide a review of the contractor's work designated by the
project structural engineer as needing special inspection under the guidelines of the IBC to determine
compliance with the approved construction documents.The special inspector doesn't have the
responsibility or authority to, nor is it the intent of special inspections to have them,judge, or modify the
construction documents. Only the structural engineer of record can do this.
As the special inspections were completed,a Special Inspectian Daily Report was prepared to summarize
the results of our inspections and testing.A copy of this report was provided to the contractor's site
representative for their review and records. As part of this report, items needing correction or
discrepancies observed from the approved construction documents were noted.
Al g.'1�:�.���, �ks�s�°t��trts����8���=_�>cbr°��t€�s��zc����.:°�a=saatt�a��pr�c�t���Itt���kr��;��tt��se���;s'%
City of Eagan
Project BL-12-04581A
August 13, 2014
Page 2
Plans and Specifications
The provided plans and specifications or the plans available at the site were used for our inspections.
Summary of Special Inspections and Material Observations and Tests
Soil Evaluation and Testing
Based on the results of our geotechnical evaluation performed for this project,subsurface conditions
generally consist of existing fill overlying native sands.Soil corrections,including the subcut and
replacement of existing fills,were performed prior to construction of the building. Excavations of about 5 to
10 feet were performed during soil corrections. Based on our observations,excavators removed old fill soils
to expose the underlying native soils.Soil corrections were perFormed within the building footprint and
oversize area.The bottom elevation and lateral extent of excavations were determined using Global
Positioning System (GPS) instrumentation operated by the contractor(Frattalone)at the time of
construction.
Excavations were backfilled with suitable on-site fill materials generally composed of a mixture of sands
(SP/SM)and clays(SC/CL). Compaction testing using nuclear density methods was performed during
backfilling and indicates that an adequate level of compaction was generally achieved.
Based on the results of our observations and testing performed during building pad preparation for Building
300,subgrade materials were judged suitable for support of structural loads and the design allowable soil
bearing capacity of 6,000 pounds per square foot(PSF).
Concrete Reinforcement
We initially reviewed the concrete reinforcement and dowel requirements on the project structural
drawings and shop drawings, if available. Information reviewed included bar size, bar length, bar spacing,
bar location,splice lengths, and dowel placement.This information was then used to determine if the '�,
inplace reinforcement was placed in general accordance with the requirements of the project plans and
specifications. We also noted if the inplace reinforcement was free of rust,scale and/or soil.
Post-Tension Cable Placement and Tensioning
With the post-tension cables installed,the cables were counted,the profile/drape of the cable (CGS)was
measured,the condition of cable and sheathing was observed and the method used to secure the cable
in place noted.The installation of the castings and the surrounding reinforcement was observed. With
the final top milled steel reinforcement in place,the backup bars and CGS bars were observed to
determine if the height tolerances were met.
During placement of concrete,the special inspector was on the deck observing the placement of the
concrete.These observations were done to document any movement of the reinforcement,cables or
cable support devices(i.e., chairs,slab bolster,CGS bars, backup bars),as these will affect the
performance of the slab. If noted, the contractor was notified that the item had moved and needed to be
repositioned.
City of Eagan
Project BL-12-04581A
August 13, 2014
Page 3
For stressing,the contractor marks each cable with a reference mark for review by the special inspector.
During the stressing,the special inspector observed the operation and the stressing gauge,and observed
the dial reading to document that the correct load was being applied to the cable.The reading on the dial
was compared to the calibration chart pressure for each ram and gauge being used. With the stressing
completed,the special inspector measured and recorded elongation for each cable using the reference
mark. Elongation measurements were compared to the estimated elongations provided on the post-
tensioning shop drawings so that any discrepancies could be documented.After final review by the
special inspector,the measured elongations were sent to the structural engineer of record for review
and approval.
Expansion Bolts and Adhesive Anchors
Observations were performed during the installation of bolts and anchors to determine if they were
installed according to the requirements of the manufacturer and the project documents. Items observed
included the placement,depth of embedment,cleanliness of the drilled hole and, if needed,the
application of the epoxy adhesive.
Concrete Placement Observations
Concrete placement observations were performed during placement to determine if the procedures
being used by the contractor are consistent with typical industry standards.
Fresh Concrete Testing
Routine tests to determine the plastic concrete's slump,temperature and air content were performed
during each concrete pour. In addition,sets of concrete cylinders were cast at rates specified in the
project specifications for compressive strength testing in the laboratory.
Concrete Compressive Strength Testing
The cast concrete cylinders were temporarily stored on site for curing and then returned to our
laboratory for moist curing and compressive strength testing.The results of the concrete compressive
strength testing were forwarded to the pertinent parties under separate cover throughout the project as
they became available.
Masonry Construction Observations
Masonry related observations performed during construction included mortar preparation,construction
of mortarjoints,and the location of reinforcement and connectors to determine compliance with the
requirements of the project plans and specifications.
The inspection program included determining the size and location of structural elements in addition to
the type,size,and location of anchors, including other details of anchorage of masonry to structural
members,frames or other construction for compliance.We also determined if the specified size,grade
and type of reinforcement was used and if the protection of masonry was in compliance with the
guidelines of the IBC.
Prior to grouting,the cleanliness of the grout space, placement of reinforcement and connectors,
proportions of site-prepared grout and construction of mortar joints were observed.
City of Eagan
Project 81-12-04S81A
August 13, 2014
Page 4
Concrete Masonry Grout Testing
The grout prisms cast were tested in generat accordance with ASTM C1019`.Standard Test Method for
5ampiing and Tes�ing Grout.The samples were temporarily stored on site and re#urned to our laboratary
for compressiue strength testing.The results for'the compressive strengths of the grout prisms were
forwarded to the pertinent parties under separate cover as they became available.
General
In performing its services, Braun Intertec used that degree of care and skil!ordinarily exercised under
similar circumstances by reputable members of its profession currently practicing in the same locality. Na
warran#y,express or implied, is made.
Thank you for the opportunity to provide special inspectian and testing services for this praject.After
review of the attached Non-Structural Steel Special Inspection Final Report if you have any questions or
requ'ire add'itional information, please feel free to contact Brad McCarter(952.995.2268 or
bmccarter@braunintertec.com) at your convenience.
Sincerely, 'I
BRAUN INTERTEC GO'RPORATION
.
����
radC� ' .� �Carter, PE
Project `ineer
# �����.�.�
� -��,,� s�
Gr��,��'�"andr ,, , PG
Vice President—Principal Engineer '
Attachment:
Non-Structural Steel Special Inspection Final Report
c. Mr.lohn Gorder, City of Eagan
Mr. Dale �onning, City of Eagan
Mrr. Dave Nelson, Frattalone Companies, Inc.
Mr. Mike Durene, PCL Construction Services, Inc,
Mr. Darin Engelby, RCl Construction Services, Inc.
Mr. Chris 7auseheck, PCL Canstruction Services, Inc.
Mr. Patrick Baugie, RSP Architects, Ltd,
Mr. ehad Davison, Stantee Consul#ing Services, Inc,
Mr.Scott Froemming, Walker Parking Consultants/Engineers, Inc.
Mr. Gary Hahn, Walker Parking Cansultan#sJEngineers, Inc.
M'r.Carl Schneeman, Walker Parking Consultants/Engineers, Inc,