09/09/2003 - City Council Public Works CommitteeAGENDA
PUBLIC WORKS COMMITTEE MEETING
Tuesday
September 9, 2003
5:00 p.m.
City Hall
Conference Room 2A/B
(2°d Floor)
I. ADOPTION OF AGENDA
II. PROJECT 817, VIBURNUM TRAIL
V. OTHER BUSINESS
VI. ADJOURNMENT
PUBLIC WORKS COMMITTEE MEETING
TUESDAY, SEPTEMBER 9, 2003
5:00 pm
I. Proiect 817, Viburnum Trail (July 2000 Storm Mitigation Improvements)
Background
As part of the July 2000 Super Storm Mitigation Improvements, during the
installation of a storm sewer pipe near the front of the property at 2099 Vienna
Lane damage was incurred by the driveway to an area approximately 2 to 3 square
feet in size at the edge of the public right-of-way. The damage was brought to the
City's inspector's attention. The on-site inspector recognized the need to correct
the situation and visibly marked an area to be removed and replaced that included
approximately 540 square feet of the driveway, up to a well defined pre-existing
crack across the entire width of the driveway. The replacement area began at the
curb and extended the full width of the driveway to the crack, about 10 feet
beyond the damaged area. This reparation of a driveway disturbed by
construction activity was in compliance with standard City procedure.
Said driveway work was completed 2 days after it was marked by the inspector
and after discussing the planned restoration with the resident, Jamie Strickland.
The day following the driveway construction Mr. Strickland contacted the City's
inspector requesting that the entire driveway be replaced. Mr. Strickland offered
a contribution to finance the portion of the driveway that had not been disturbed.
Mr. Strickland was told that this would not be possible since the paving contractor
had completed his work within the project area.
On April 5, 2002, the City Engineer met Mr. Strickland at 2099 Vienna Lane to
discuss the concerns with the driveway reparation and the resident's desire to
have the entire driveway replaced. During this meeting, 3 main concerns were
stated about the driveway by the resident;
• Separation at the construction joint
• Perpendicular crack at the east end of the construction joint
• Color differentiation between the old and new driveway.
The City Engineer's inspection of the driveway, indicated the following.
• The construction joint was straight, neat, level and tightly abutted the
remainder of the pre-existing driveway. There was no apparent separation.
• There was a small crack, about 10" long, at the east edge of the new driveway
section, perpendicular to the construction joint. The cracked area was on the
opposite side of the area where the storm sewer construction activities
occurred. It is unlikely that the damage occurred during construction, or that
the driveway was damaged by the construction activity related to the storm
sewer work. The driveway may have been damaged by a vehicle parking on
the edge of the driveway, with a tire partially on the less compacted turf area.
• The color differentiation between the old and new driveway surfaces was to
be expected. Within 3 years after construction, the color differentiation will
be very slight, if noticeable.
At the close of the meeting, the City Engineer suggested that Mr. Strickland
pursue any previous arrangements regarding the driveway replacement made with
the contractor and that the City of Eagan would not be responsible for additional
driveway improvements. In discussing this matter with the contractor and the
City's consultant engineer who provided the inspection services, it appears that no
arrangements were previously made. The City Engineer has reiterated to Mr.
Strickland on multiple occasions since the April, 2002 meeting that no further
driveway work is expected to be completed at the residence as a part of this
contract.
Issue
Mr. Strickland is not satisfied with City staff's response to his request and has
asked that the City Council address his request for restoration of the entire
driveway. The City Council has directed that the matter be addressed by the
Public Works Committee.
Options:
1. Provide a recommendation to provide additional driveway improvements for
full Council ratification at a future Council meeting, OR
2. Deny the request.
Attachments:
• City Engineer's letter, pages 3 and L
• Mr. Strickland's E-mail Correspondence, pages and �.
• City Engineer's E-mail Response, pages and.
• Photos of current conditions, pages I_ to
• Original Plan design, page -/46-.
C:?
416�citV OF eagan
May 7, 2002
PATRICIA E. AWADA
Mr. Jamie Strickland
Mayor
2099 Vienna Lane
Eagan, NN 55122
PAUL BAKKEN
Re: Project 817, Storm Mitigation Improvements — 2099 Vienna Lane
PEGGY CARLSON
CYNDEE FIELDS
Dear Mr. Strickland:
IVIEGTILLEY
I am writing as a follow-up to our numerous telephone conversations, messages and meeting on
Council Members
site regarding the construction of the July 2000 Storm mitigation improvements within your
property. Our correspondence has dealt specifically with the restoration of your bituminous
driveway.
THOMAS HEDGES
I would like to apologize for your expressed frustration with the construction activity and
City Administrator
disturbance within and adjacent to your property. I assure you that all of the restoration issues
that have yet to be completed will be completed as originally indicated in the plans and
specifications for the contract as quickly as possible. Restoration of your yard, including the
paver brick patio, lilac bushes, landscaping rock and associated landscape material and edging
Municipal Cerner:
will be completed as stated in the letter I wrote dated July 23, 2001. Restoration of any settled
3830 Pilot Knob Road
portions of the utility trench impacting the street, curb and gutter or your yard will be addressed,
as stated in the contract specifications.
Eagan, MN 55122-1897
Phone: 651.681.4600
To clarify your concerns regarding the driveway, I will restate the occurrences affecting your
driveway related to the public improvement. As part of the installation of the storm sewer pipe.
Fax: 651.681.4612
near the front of your property, damage to your driveway occurred to an area approximately 2 to
TDD: 651.454.8535
3 square feet in size at the edge of the public right-of-way. The damage was brought to the City's
inspector's attention and you asked how the damage would be addressed. The on-site inspector
recognized the need to correct the situation and visibly marked an area to be removed and
Maintenance Facility:
replaced that included approximately 540 square feet of your driveway, up to a well defined pre -
3501 Coachman Point
existing crack across the entire width of the driveway. The replacement area began at the curb
and extended the full width of the driveway to the crack, about 10 feet beyond the damaged area.
Eagan, MN 55122
This reparation of a driveway disturbed by construction activity is standard City procedure.
Phone: 651.681.4300
j
Said driveway work was completed 2 days after it was marked by the inspector. The day
Fax: 651.681.4360
following the driveway construction you contacted the City's inspector requesting that the entire
TDD: 651.454.8535
driveway be replaced. You offered a contribution to finance the portion of the driveway that had
not been disturbed. You were told that this would not be possible since the paving contractor had
completed his work within the project area.
www.cityofeagan.com
This spring you contacted me about your concerns with the reparation of your driveway and your
desire to have the entire driveway replaced. We scheduled a meeting at your residence on April
5, 2002, and I viewed the driveway with you. During this meeting you stated 3 main concerns
about the driveway: separation at the construction joint, perpendicular crack at the east end of the
THE LONE OAKTREE
construction joint and color differentiation between the old and new driveway.
The symbol of strength
and growth in our
community
3
My inspection of the driveway, specifically in regards to your concerns, indicated the following. The
construction joint is straight, neat, level and tightly abuts the remainder of the pre-existing driveway.
There is no apparent separation. There is a small crack, about 10" long, at the east edge of the new
driveway section, perpendicular to the construction joint. The cracked area is on the opposite side of the
area where the storm sewer construction activities occurred. It is unlikely that the damage occurred
during construction, or that the driveway was damaged by the construction activity related to the storm
sewer work. The driveway may have been damaged by a vehicle parking on the edge of the driveway,
with a tire partially on the less compacted turf area. The color differentiation between the old and new
driveway surfaces is to be expected. Within 3 years, the color differentiation will be very slight, if
noticeable.
At the close of our meeting I suggested that you discuss any previous arrangements regarding the
driveway replacement that you may have made with the contractor and that the City of Eagan would not
be responsible for additional driveway improvements. In discussing this matter with the contractor and
the City's consultant engineer who provided the inspection services it appears that no arrangements were
previously made.
No further driveway work is expected to be completed at your residence as a part of this contract. It is
regrettable that damage to your driveway inadvertently occurred as part of the construction of the
drainage improvements. However, the restitution appears to be more than adequate.
I can appreciate your concerns with the impacts this construction work has had on your property. I also
understand that your home was not flooded by the July 7-9, 2000 Storm and that you permitted the
drainage improvements to be constructed on your property to assist your neighbors. Your cooperation to
allow the construction of these critical drainage improvements is greatly appreciated by the City, as I am
sure that it also is by your neighbors.
Sincerely, p
Russ Matthys, P.E.
City Engineer
Cc: Mayor & City Council
c/o Thomas Hedges, City Administrator
Thomas Colbert, Public Works Director
Mark Hanson, Consultant (BRAA)
G:R W01/Letters/Proj 317, DrwyStricklmd
Jamie Strickland
2099 Vienna Lane
Eagan, MN 55122
651-905-1263
952-844-4297
Russ Matthys
I am writing to explain our ongoing dissatisfaction with the results of the Storm
Mitigation Improvements of 2001.
It is important that I first begin by stating that none of the stated repairs would
benefit us, as we have never experienced any water seepage or damage.
Everything about this project has inconvenienced us. We had days where our mail
wasn't delivered as the contractors blocked our mailbox and never put up temporary
mailboxes. Our yard was a large and lengthy mud pit for an unreasonable amount of
time. We lost well over one dozen large, mature Lilac bushes. All the landscape rock
from the West side of our house was removed. We lost cable as the contractors cut
our cable. You personally assured me both verbally and in writing that any damage
to our paver patio would be repaired. This is an item that still remains to be
addressed as I cannot locate the original contractor who installed our patio and it
DOES need to be repaired. It now has a larger angle of descent as well as loose
pavers due to the extreme amount of vibration from the heavy equipment.
Our largest complaint centers on our driveway. For whatever reason, the contractors
drove heavy equipment across our driveway and damaged the west side of our
driveway. The Bonestroo crew was going to replace the entire lower half of our
driveway. I explained to Ryan and the Bonestroo representative that I did not want
half of our driveway replaced. Instead, I offered to pay a fair amount for the other
half of the driveway and then have the entire driveway replaced. No one ever got
back to me and when I finally got a hold of someone, the asphalt was being laid. My
permission was never granted for this unsightly repair. It is worth noting that there
was no permission or easement requested or granted regarding our driveway. The
driveway repair was done without our consent and against our wishes.
After a second winter now, the crack between the two sections of driveway has
widened and more of the driveway at the crack is crumbling apart. There are also a
few pieces from the east side of the new section of driveway that have cracked off.
Our entire driveway MUST be replaced, as it looks terrible. If we needed to sell our
house, this would without question affect any potential sale. There are two distinctly
different textures and colors to our driveway. Worse yet, the paving job was done
very poorly and in haste. The new section is uneven and has a sinking spot. The
edge has cracked off on the east side and this was blamed on my parking. No, it's
inferior materials. Also, it wasn't installed with proper equipment, as there is a
definite "seam" down the middle of the new section. I have witnessed a driveway
installation and a correct installation uses a machine that is as wide as the driveway,
not half the width.
S
Our second largest issue has been our yard and landscaping restoration. After about
9 months of dirt and mud, we finally had sod delivered. Instead of delivering the sod
in the early spring where there would have been plenty of rain and cooler
temperature, they decided to install the sod the last week of June while we were in
the midst of 900+ days with high humidity. NO TOP SOIL was brought in and the
sod was installed over the top of hard, packed dirt. So after about 2 weeks, the sod
crew was back out replacing ALL of our sod. There are still several areas where we
have patches of dead sod or sod that is pulling apart at the seams. About a month
after the sod fiasco, we finally had our replacement trees delivered. Not anywhere
near as large as the Lilac bushes that were removed, 8 Lilac bushes were planted
and just before cold weather set in, 3 of the Lilac and 2 of the 3 Evergreens died.
Compounding the issue was that all of our landscaping rock that was removed had to
be reinstalled by me. I was not compensated for my time or my materials other than
the rock itself.
In summary, we were the only ones primarily inconvenienced by this yet we also
take no benefit from this improvement. We gave the city our permission for this
improvement under the assumption our property would be restored to its original
condition. Sure, we have new bushes and trees, but nearly half our dead, all the sod
has been replaced once, our paver patio is damaged, we had a cable outage over a
weekend and worse of all, our driveway looks terrible.
Jamie Strickland
nw,
Russ Matthys
From: Russ Matthys
Sent: Thursday, May 22, 2003 5:52 PM
To: 'Strickland, Jamie'
Cc: Tom Colbert; John Gorder
Subject: RE: Storm Sewer Mitigation Feedback
Jamie,
Sorry for the slow response. I forwarded your message to see how it should best be
addressed. The determination was made that since it was related to Public Works
activities as part of the July 2000 Storm Improvements, it should go to the Public Works
Committee for their recommendation to the City Council. The Public Works Committee is
made up of two Council members.
In order for the Public Works Committee to be best informed of the extent of your claim,
it would be appropriate to provide them with cost estimates for the requested work that
would satisfactorily address your concerns:
Just so we are on the same page and you don't have to make any extra effort, I will
address some items in your letter that I expect to still address, if they haven't been
completed already.
I can understand if you can't locate your original contractor who constructed your paver
patio. How about finding someone else who would relay the corner of the patio to your
satisfaction and send us the bill when it is completed? I believe this would be
equivalent to what we had previously discussed.
The lilac bushes and evergreens are under warranty and will be replaced, if they haven't
been already. The sod deficiencies will also be addressed. As we had discussed, in the
areas where there are small gaps between the sod, topsoil and seed will be placed to
produce a better end product. Has any of this work been completed yet?
As I understand your concerns, the driveway replacement is the only outstanding issue that
I'm not able to address to your satisfaction. That being the case, would you please
detail the specifics of the driveway work you would like to have completed to satisfy you.
A copy of a detailed cost estimate from a contractor would be great.
I will be out of the office for the next 2 weeks, beginning Monday, May 26. I can present
any information you get back to me to the committee after I return on Monday, June 9.
Thank you for your patience.
Russ Matthys, P.E.
City Engineer
City of Eagan
651-675-5646
FAX 651-675-5694
rmatthys@cityofeagan.com
-----Original Message -----
From: Strickland, Jamie[mailto:strickla@BIWORLDWIDE.com]
Sent: Friday, May 09, 2003 12:43 PM
To: 'Russ Matthys'
Subject: RE: Storm Sewer Mitigation Feedback
Thanks a lot Russ. I know I have been a thorn in your side for some time but I do
appreciate you advice, assistance and patience with me.
Jamie
-----Original Message -----
From: Russ Matthys[mailto:RMatthys@ci.eagan.mn.us]
Sent: Friday, May 09, 2003 11:55 AM
To: Strickland, Jamie
Subject: RE: Storm Sewer Mitigation Feedback
Jamie,
I received your e-mail. I will forward the attachment with a request for the City Council
to consider the replacement of your driveway. I will notify you of any scheduled
consideration by the City Council. Please contact me with any questions.
Russ Matthys, P.E.
City Engineer
City of Eagan
651-675-5646
FAX 651-675-5694
rmatthys@cityofeagan.com
-----Original Message -----
From: Strickland, Jamie[mailto:strickla@BIWORLDWIDE.com]
Sent: Friday, May 09, 2003 9:13 AM
To: 'rmatthys@ci.eagan.mn.us'
Subject: Storm Sewer Mitigation Feedback
<<RussMatthys.doc>>
Jamie Strickland
Java Developer
BI netData Services Group
Phone: 952.844.4297
Email: mailto:strickla@biworldwide.com
www.biperformance.com
F' 7:
� is 4• ..
P
- =..f..
> -M1 5 ':' 16 � y-4 >��"moi-�F''hh �rtY. i:�}�jaS�•
F' 7:
� is 4• ..
P
io
R� �y•�
� Vii•+►!
d
,.,� '
,� '#' , �,
;
l
-
e t
.. ; 4. a +. � *, � � , `� �� a" � .. a' i. �- x k • - -. • pr � '
* a - r * e � � a� f� �.�". � mow. �,� y '.•' ; � w. � �-.
A t _ • t F i� may.,
ryy' `K ' ,
q •!• x aT' y SY r'-1-}
k®r kill
t ,{y€*`,r0. a 4 -+ xt. � •� s , - .
�7
L
zL �.s.. _ .�-
,, -
_ .. _ .�
,� �
�=� � _
��� �� �
w�,�� ��,
��� ��
�~ '�' _ �
_: _ r
,_
r g � _ �. _ �
a
C>
a �
a'
s
. ♦
F
r ,
` 7
#
�- - ±�bti-.3 sir � +r"
s tty ;.�, � 4., ,
�.
1
56 � Y y
� `' i
1:l ��� � +
F �'' ��, #
a
f
,� .'yy". �tig ,� �.
.f
� �b �.
Oak Way
o
_
I� 934.4
1 I
l
I
934,
� I I j �" m a II
—moi
--I
935.1mo
J L_ IZ I I
ill
o
— — — I
I
I
R- i
921.95-18
1+ 7
— — —
A l ------ i--
r x m f
- -------
JI -i
_ 935.8
;�I f L — — — —
I o=
I� I I
IVlenno La.
L ' N r� o
Z—j r
+
935.7
; C I g z I oco
; y
m
j G I I
0
m I
p
—J
t
I I I
rr--
I
927.19-12"
936.0
z t r -
-\ _� N f�-
1�� \ \ i - -t _ �� 0 o
ra I I
�"'
936.5-
\
!� $ j +r,• / rD�� 1 o f �j % \%% z m g
0 I I
+50f
m
934.8
\' / •.r• r o A� •�-- ` — — -
En
� \ \ { m
> \ '.'
�x
I—
0 oA
935.3
o �I j 1 c\– It—� p
f
m l i
\1
m 0
932.7
0 5 / z n
a• it
� 0.4.
I I p
\ ` � m i • r C
J
I I
I I
m
z � Z
��\,� • i f m
'• I
I I
Nr••
t
930.8
m lam_ y
/1 "'----- __.l 0 A.
\ i / -0 m0
I z <A
5+27
C
l
—�-
I_lJ
I
927.48
930.9
\ m
6 y
-2
1
931.7jK)
jt0
O
L4460
co
co
j0
O
O
O
"'
N 01 D
D
�N<p-Al
my mml
mmv�C.'m
�m=1
Z
>oz-ma'z
m W (n�_
0;00 0
a 2
D Fn iA D
F--119
0 ;a m
V)r
Z z >
-q O r0
o
_•' / v !
¢ I i..
1 N. (_...__.
00
c M R
�
� D
�...
p
c y i.
y
zQzDm
O `r�+ 1
y
Cy�Cy
�p
yy D
m
>�
c
y0D
gInn-may
;pp
Z M m
c ^¢
� oo�Ooa'-^�'
=j:d'V
DZV
-4Rl
1
ola
px
�c
f^ tn
c0
n "
yz{
z _
m
Tmy
m N CA
pymr�
n r�+
_
jjIIII
4
co
co
w � ,
y
e y N LJ
R hn Road Arm