09/12/2017 - City Council SpecialSPECIAL CITY COUNCIL MEETING
TUESDAY, SEPTEMBER 12, 2017
5:30 P.M.
EAGAN ROOM
EAGAN MUNICIPAL CENTER
AGENDA
I. ROLL CALL AND ADOPTION OF THE AGENDA
II. VISITORS TO BE HEARD
III. GREATER MSP PRESENTATION
IV. POLICE DEPARTMENT AND CITY HALL REMODEL SCHEMATIC DESIGN
V. JOINT MEETING WITH ADVISORY PARKS & RECREATION COMMISSION
• Parks and Recreation 2018-2023 Capital Improvement Plan
VI. OTHER BUSINESS
VII. ADJOURNMENT
Agenda Information Memo
September 12, 2017, Eagan Special City Council Workshop
III. Great MSP Presentation
Direction for Considered:
None. Greater MSP officials will be in attendance to provide an update on the activities of the Greater
MSP.
Facts:
The City of Eagan is an original member of the Greater MSP, a Minneapolis-St. Paul Regional
Economic Development Partnership; contributing $25,000 annually.
Judy Johnson, Director of Investor Relations; Matt Lewis, Director of Make. It. MSP and Joel
Akason, Senior Director of Business Investment, will be in attendance at the Special City Council
workshop on September 12, 2017 to provide an update on the activities of the Greater MSP
Attachments: (1)
III.-1 Greater MSP Presentation
Business and people prosper here
City of Eagan Presentation – September 12, 2017
THE GREATER MSP REGION Mille Lacs Isanti Sherburne
Wright
Hennepin
Carver
Sibley
Le Sueur
Scott Dakota Pierce
St. Croix
Washington
Chisago
Anoka
Ramsey
16-COUNTY MSA $249 BILLION
42th LARGEST
GLOBAL ECONOMY
IN GMP
3.5 MILLION PEOPLE
MORE THAN
Updated March 2017
PROSPER: MOMENTUM IS BUILDING
REGIONAL SECTORS OF STRENGTH
•BIO TECH
•HEALTHCARE PROVIDERS
•HEALTHCARE PAYERS AND IT
•MEDICAL DEVICES
•R&D CENTERS
•SOFTWARE/ IT
•ADVANCED MANUFACTURING
•ENERGY/RENEWABLES
•FINANCIAL ADVISORY
•BANKING
•INSURANCE
•CORPORATE HEADQUARTERS
•CREATIVE SERVICES
•PROFESSIONAL SERVICES
•DATA CENTERS
•FOOD PROCESSORS
•FOOD PRODUCTION
•AGRIBUSINESS
•NUTRITION
•WATER FILTRATION
•WATER PURIFICATION
FINANCIAL SERVICES
ADVANCED MANUFACTURING & TECHNOLOGY
HEALTH & LIFE SCIENCES
HEADQUARTERS & BUSINESS
SERVICES
FOOD & WATER SOLUTIONS
PROSPER: MOMENTUM IS BUILDING
GREATER MSP HISTORY, VISION AND MISSION
VISION
The Greater MSP Region is recognized as a globally leading economy
where business and people prosper.
REGIONAL ECONOMIC
DEVELOPMENT
STRATEGY
JOB RETENTION,
EXPANSION, &
ATTRACTION
MARKETING,
BRANDING, &
PROMOTION
MISSION
Accelerate job growth and capital investment in the Greater MSP region.
PROSPER: MOMENTUM IS BUILDING
(July 2017)
GREATER MSP BOARD OF DIRECTORS
CHAIR | Richard Davis
U.S. Bancorp
IMMEDIATE PAST CHAIR |
Tim Welsh, U.S. Bancorp
VICE CHAIR | Ken Powell
General Mills
TREASURER | Ginny Hubbard
Morris
Hubbard Radio
SECRETARY | Kate Wolford
McKnight Foundation
CEO | Michael Langley
GREATER MSP
Kedrick Adkins | Mayo Clinic
Doug Baker | Ecolab
Andy Bessette | Travelers
Companies
Commissioner Jan Callison |
Hennepin County
Mayor Chris Coleman | City of
Saint Paul
Albert J. Colianni | Marquette
Companies
Gary Cunningham | Meda
Ben Fowke | Xcel Energy
Commissioner Kathleen Gaylord
| Dakota County
Todd Hall | Cargill, Inc.
Brad Hewitt | Thrivent Financial
Mayor Betsy Hodges | City of
Minneapolis
Eric Jolly | MN Philanthropy
Partners
Eric Kaler | University of MN
Mayor Elizabeth Kautz | City of
Burnsville
J.D. Keller | Comcast
Rick King | Thomson Reuters
Jay Lund | Andersen Corporation
Tim McGough | McGough
Construction
David Mortenson | Mortenson
Company
Russ Nelson | NTH, Inc.
Ravi Norman | THOR Companies
Laura Oberst | Wells Fargo
Chris Policinski | Land O’Lakes, Inc.
Commissioner Victoria Reinhardt|
Ramsey County
R.T. Rybak | Minneapolis
Foundation
David Saggau | Great River Energy
Todd Senger | BMO Harris Bank
Marianne Short | UnitedHealth
Group
Commissioner Rhonda Sivarajah |
Anoka County
John Stauch | Pentair
Carol Surface | Medtronic plc
Commissioner Jon Ulrich | Scott
County
Charles R. Vig | Shakopee
Mdewakanton Sioux Community
Andrea Walsh | HealthPartners
Laysha Ward | Target
Kevin Warren | MN Vikings
Commissioner Lisa Weik | Washington
County
“2016 saw the addition of two data centers to the Greater MSP region. In the world of big data, data centers are an
increasingly important element of corporate infrastructure. Our region is a great location for the centers thanks to
an abundance of cool air and low occurrence of natural disaster. These project have a modest job count associated
with them, but bring a significant amount of capital investment, tax base, and related economic impact due to
frequent equipment upgrades, installation, and maintenance. Data centers also are large and very efficient users of
existing electrical infrastructure, which helps lower the rates for all consumers. Data center projects have become a
staple in our region, and one we hope to continue to see.”
Mark Loftus, Economic Development Director, Dakota Electric
GREATER MSP Investor/Partner
Dakota County Leaders – Supporting & Engaging in the GREATER MSP Partnership
“The Regional Indicators Dashboard emphasizes the great power and capability that is in the region. It illustrates it in facts.
The Dashboard has helped us to tell a better story about the area and recruit the people we want here.”
Rick King, CIO-Technology, Thomson Reuters
GREATER MSP Board Member
Co-Chair of the MSP Regional Air Services Partnership
GREATER MSP Investor/Partner
Business Attraction
Research
BUSINESS INVESTMENT
Business Retention & Expansion
Export Development Foreign Direct Investment
WHAT REGIONAL ECONOMIC DEVELOPMENT
ORGANIZATIONS DO:
PRE-DEAL
•Define regional strategy
•Present “face of the region”
(regional brand)
•Proactive out-reach to
companies
•Respond to company
inquiries
•Provide regional data
•Coordinate CEO/existing
business engagement
•Assist with site selection
CLOSING THE DEAL
•Present incentive options
•Mediate deal process
•Issue press release
•Connect company to local
logistics as needed
•Connect company to
training
OTHER DELIVERABLES
•Talent Recruitment
•Convene local industry groups
•Advocacy
(Source: Boston Consulting Group,
“Regional Economic Development Benchmarking”
January 2017)
Commissioned Studies
Business Costs Comparison
Workforce & Labor Shed Analysis
RESEARCH:
PROSPER: MOMENTUM IS BUILDING
Better Data = Smarter Decisions
Perception Studies 2012 & 2015
PROSPER: MOMENTUM IS BUILDING
4.0
2.0
3.0
2012 2015
2.3
3.0
3.4
2012 2015
3.0
RESEARCH: Business Perception Study - largest improvement in
over 3 years
How likely are you to consider
MSP for future projects?
(1=Not Likely, 5=Very Likely)
What is your perception of the
business climate in MSP?
(1=Very Bad, 5=Very Good)
PROSPER: MOMENTUM IS BUILDING
Economic Overview
Eagan
Compared to the MSP
metro, Eagan has:
•More professional jobs,
particularly
computer/mathematical
•More residents with BA’s
and higher
•Lower unemployment
•Higher home values
Source: ESRI.
Definition of Tapestry Segments (lifestyle choice segments):
•Bright Young Professionals is a large market, home to young, educated, working professionals. Slightly more diverse couples dominate this market, with more renters than homeowners.
•Professional Pride consumers are well-educated career professionals that have prospered and maintain an upscale suburban lifestyle, are goal oriented working couples that commute, have school age children and are financially savvy.
•Savvy Suburbanites are well educated, well read, and well capitalized. Families include empty nesters or those with adult children at home. Located in older suburgan neighborhoods, they pursue home remodeling, gardening, exercise, food and wine, and cultural events.
•Population 67,528 – 8th
Largest City in Minnesota
RESEARCH: Utility Partners and Network Fiber Speed
GMSP works with our utility company
partners such as Xcel and Dakota Electric
on Business Investment projects.
To support services to customers in the
region, GMSP commissioned two studies:
•Latency Study – Assessment of data
speeds to/from our metro to rest of
U.S.
•Connectivity Study & Map - Unique,
detailed interactive map of data
connectivity availability.
PROSPER: MOMENTUM IS BUILDING
New Tool – Interactive Map of Connectivity Availability
Source: U.S. Census Bureau OnTheMap, Local
Employment – Household Dynamics 2014
PROSPER: MOMENTUM IS BUILDING
RESEARCH: Eagan Resident & Worker Inflow/Outflow
(workers coming in) (workers going out)
(workers who live and work)
PROSPER: MOMENTUM IS BUILDING
Eagan Project Wins
City Project Facility Type Total Project Investment Expansion SF
New Jobs
Touch
(Est. w/i 5 yrs.)
Eagan Corvida Manufacturing $3,100,000 0 30 Medium
Eagan Veritas Software $12,000,000 7,000 8 Heavy
Eagan Ginovus $7,500,000 60,000 10 Medium
Eagan Convergys Corp $2,000,000 100,000 300 Heavy
Eagan Prime Therapeutics $7,000,000 100,000 450 Heavy
Eagan DataBank $48,635,000 93,000 30 Medium
Eagan Convergys Corp $1,000,000 100,000 300 Heavy
Total $81,235,000 460,000 1,128
GREATER MSP Regional Business Development Initiatives
PROSPER: MOMENTUM IS BUILDING
COORDINATED MARKET VISITS, TRADESHOWS, BROKER EVENTS
2016 Domestic & International Outreach Representing Entire Region
PROSPER: MOMENTUM IS BUILDING
History of Job Growth – Greater MSP Region
Stagnation
GREATER MSP
Partnership
Created
PROSPER: MOMENTUM IS BUILDING
REGIONAL
STRATEGY
TELL OUR
STORY
PRIORITIZE
TALENT
BUILD GLOBAL
SECTORS
2014 – 2018
MSP REGIONAL INDICATORS DASHBOARD – Tracking Our Competitiveness
MSP REGIONAL INDICATORS DASHBOARD – Reading the Dashboard
AUSTIN
PHOENIX
GRAND
RAPIDS
TALLAHASSEE
SAN DIEGO
SEATTLE
SYRACUSE
PORTLAND
LOUISVILLE
MEMPHIS
CHICAGO
RIVERSIDE LEXINGTON
FORT COLLINS
INDIANAPOLIS
15 U.S. regions reach out to learn about the MSP Regional Indicators Dashboard
PHILADELPHIA
MSP REGIONAL INDICATORS DASHBOARD – Moving Data Into Action
May: Dashboard Release August: Dashboard Workshop New: Quarterly Newsletter
114,000 Potential MSP Worker
Shortage 2020
Low
Unemployment
High Workforce
Participation +
Racial
Disparities + Increasing
Diversity
Moderate
Attraction + Falling Organic
Growth
Regional Workforce Equation
Competing to retain and attract top talent
*U.S. states and regions are accelerating their
talent migration efforts, experimenting with new
solutions, and learning from each other.
Examples are illustrative, not comprehensive
Using data to drive decisions
MSP is among the nation’s best major metros
at retaining professional talent, but trails
peers at retaining diverse professional talent
and attracting talent overall
Perception analysis of more than 5,000
professionals within and beyond MSP helped
inform strategies on attracting, onboarding, and
retaining. For example, national perception of MSP
is low, but people are willing to consider the area
ENTERPRISE NEWCOMERS TECH STARTUP PROFESSIONALS
OF COLOR
Scott Swayne
General Mills
Lisa Vongchingtrong
Target
Nick Roseth
DocuMNtary
Lauren Hunter
State of Minnesota
Damola Ogundipe
CODE2040
Shared platform for regional collaboration
•500+ employer
talent leaders
receive MSP
Talent Tips
updates
•40,000 unique
visitors to
makeitmsp.org
•2,500+ new
residents
subscribed to MSP
Hello welcome
program
•10,000+ welcomes
at events and via
team website
•3M+ impressions
to 330,000+ tech
professionals in
targeted U.S.
metros
•Company-led
market visits and
fly-in program
•1,200 in-depth
insights on
retention and
inclusion in MSP
region
•Thousands of
attendees at MSP
Mingle events
•15,000+
participants at
150+ events this
Twin Cities Startup
Week
•Microtargeting to
tens of thousands
in key markets
To help protect your privacy, PowerPoint has blocked automatic download of this picture.
Working to make this the best place in the world for talented
people to come, stay, and thrive.
Business and people prosper here
Thank you for your partnership and support!
Special City Council Workshop
September 12, 2017
IV. Police Department and City Hall Remodel Schematic Design
Action to be Considered:
To provide feedback to staff and the architectural team on the proposed schematic design and
budget for the Police Department and City Hall remodeling efforts.
Facts:
On May 2, 2017, the City Council approved a contract with Wold Architects and
Engineering for architectural design services and construction support for building
improvements at the Police Department and City Hall.
Over the past four months, Wold, along with Assistant City Administrator Miller and
Director of Parks and Recreation Pimental, have led an inclusive and participatory process
with City staff to prepare schematic designs of the building modifications.
John McNamara, Wold Partner-in-Charge and lead architect on the project, along with
Architect Melissa Stein, will be at the September 12 workshop to brief t he Council and
seek feedback on the proposed schematic design and project budget .
Pending feedback from the Council, the architectural team will continue their dialogue
with the City’s project leadership team and staff teams as the designs and project ar e
further refined.
It is anticipated that a final design will come before the City Council at the November 14
Council workshop, with final approve at the November 21 City Council meeting.
The project is proposed to be bid in the first quarter of 2018, with construction
beginning in late spring/early summer 2018, following award of the contract and sale of
bonds. The project will likely be complete in early to mid-2019.
At the workshop, City Administrator Osberg and Finance Director Pepper will walk
through the proposed funding sources for the City’s capital building projects.
Attachments:
IV-1 Presentation on Proposed Schematic Design
IV-2 Funding Considerations
Eagan City Hall and Police
City Council Meeting
September 12, 2017
Agenda
1.Guiding Principles
2.Space Summary
3.Site Plan Solution
4.Proposed Layout
5.Project Schedule
6.Budget
7.Next Steps
Guiding Principles/ Statements:
»Anticipate the needs of the City for the next 20 years. The facility needs to
consider the long-term build out of the City.
A comfortable work environment which staff and city takes pride in.
»Strive for a safe, yet open and publicly welcoming facility.
»The facility should encourage efficiency, interaction and collaboration among
all departments.
»Achieve best function and natural workflow organization for the department,
not just expansion.
»Provide secure parking to protect the City’s investment in vehicles and
technology.
»Better evidence/property management, processing and storage.
Guiding Principles
Space Summary
City Hall:
Lobby
Council Chambers
Administration
IT
Planning/ Zoning
Engineering
Parks and Recreation
Staff Support
Police:
Command Staff
Records/ Lobby
Patrol
Investigation and Evidence
Prisoner/ Processing/ Holding
Fleet Service/ Vehicles
Staff Support
Existing
1,800 S.F.
2,226 S.F.
4,241 S.F.
570 S.F.
3,505 S.F.
3,445 S.F.
2,789 S.F.
5,572 S.F.
TOTAL:24,148 S.F.
Schematic Design
1,638 S.F.
2,226 S.F.
3,574 S.F.
1,431 S.F.
3,114 S.F.
2,867 S.F.
1,851 S.F.
10,471 S.F.
29,291 S.F.
Existing
2,456 S.F.
2,974 S.F.
5,143 S.F.
4,117 S.F.
2,683 S.F.
1,229 S.F.
4,052 S.F.
TOTAL:21,639 S.F.
Schematic Design
2,353 S.F.
3,237 S.F.
5,740 S.F.
7,508 S.F.
2,453 S.F.
21,175 S.F.
4,549 S.F.
47,014 S.F.
Space Summary
City & Police Departments:
City Hall
Police Department
Schematic Design
29,291 S.F.
47,014 S.F.
TOTAL:76,305 S.F.
Existing
24,148 S.F.
21,639 S.F.
TOTAL:45,787 S.F.
Site Plan
City Hall
Addition
Training Room
Police
Garage
Addition
Police
Addition
Potential
Parking lot
Expansion
Police Squad
Entry/ Exit
Reconstructed
Plaza
Secure Fence
Secure
Fence
City Hall
CITY HALL MAIN LEVEL
City Hall
CITY HALL UPPER LEVEL
Police
POLICE MAIN LEVEL
Police
POLICE MAIN LEVEL GARAGE
Police
POLICE UPPER LEVEL
Building Additions
Police
Garage
Police
Addition
Training
Room
SWAT
Garage
City Hall
Addition
Police
Vestibule
City Hall
Vestibule
Existing
City Hall
Existing
Police
Project Schedule
Budget
Construction Costs
Site Preparation
Architectural/ Structural
Mechanical
Electrical
$850,000
$ 6,150,000
$4,100,000
$1,600,000
$12,700,000
Project Costs
Fees and Testing
Furniture, Equipment, Move Costs
Contingency
$ 1,250,000
$1,000,000
$750,000
$3,000,000
Subtotal Construction Costs
Subtotal Project Costs
TOTAL PROJECT COST $ 15,700,000
QUESTIONS?
Funding Considerations
2016 and 2018 Facilities CIP Projects
Current
Estimates
Sources
2016 bond proceeds 8,452,829$
Utility Fund - CMF Phases 1 & 2 1,250,000
Projected Water Quality/Grant - pervious parking 250,000
General Fund balance (2016 transfer)3,147,000
Donations 10,000
Sale of FAB, net of expenses 468,294
Estimated 2018 bond proceeds, net of costs 18,191,026
Total sources 31,769,149$
Uses
2016 - CMF Phase 1 costs (excluding screening wall)7,877,828$
2016 - New Fire Station 1 costs 5,883,321
2018 - CMF Phase 2 estimate 2,308,000
2018 - Police/City Hall estimate 15,700,000
Total uses 31,769,149$
Annual debt service (DS) levy impact by year:
2016 existing annual DS - "ceiling" (ECC bonds + bridges levy)$ 2.3 M
2017-2023 annual DS (ECC + bridges + 2016/2018 bonds)$ 2.3 M
2024-2037 annual DS (2016/2018 bonds) $ 2.2 M curr + 50 bp
$ 2.3 M
In the event of higher project costs or interest rates than anticipated, or if the Council wishes
to reduce the amount borrowed, the following funding sources could be utilized:
Sale of old Fire Station 1 and Fire Station 5 450,000$
12-31-16 General Fund balance in excess of 45%2,407,599
The City could borrow more and still stay within the $2.3M self-imposed annual "ceiling":
Additional debt capacity @ current rate + 50 basis points 1,260,166
Additional debt capacity @ current rate + 100 basis points 83,953
Other potential one-time savings from debt structuring, not factored in above:
Present-value savings from refunding of ECC bonds 136,098
Capitalized interest reduction from splitting new debt between 2018 & 2019 340,000
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Capital/Debt Service Levies
2018 bonds (+100bp)
2018 bonds (+50bp)
2016 bonds
Bridges/Exchanges
ECC Bonds
Agenda Information Memo
September 12, 2017 Eagan Special City Council Workshop
V. 2018 – 2022 Parks CIP And Joint Meeting With APrC
Direction For Consideration:
This is an informational item and discussion, therefore no specific action is required. Pending
Council’s direction, the CIP will be included on a future regular City Council consent agenda for
formal action.
Facts:
The Advisory Parks and Recreation Commission meets annually with the City Council to
have dialogue that is important to their advisory work with respect to the Parks and
Recreation Department.
As part of the joint meeting, Director Pimental and staff will present the 2018 – 2022 5
year Parks CIP program.
In 2016 the presentation during the joint meeting with the APrC focused as much on the
state of the parks, as it did the CIP.
That information presented last year has laid the foundation for continued work on the
CIP to emphasize a balance of adding new items and repairing old items/structure over
time.
The Parks and Recreation Master Plan completed in 2015, along with feedback from
Eagan Forward, as well as opportunities identified by community engagement have led
to discussions with the APrC commissioners.
New components added to the park system will highly complement the current park
system, and other projects will renew critical components of the park system.
Proposed CIP for 2018 will be a big focus on the presentation, and will total $1,660,000
in projects for the year. The higher value does reflect moving the Skate Park project
from 2017 to 2018.
Funding for the Parks CIP does come from park dedication fees through developments
as they are permitted within the City, as well as, a dedicated levy for supporting parks.
The 2018 effort is a continuation of efforts in creating a nicely balanced park system
that has a balance of amenities for all ages and built throughout the City.
Attachments: (2)
V.-1 Copy of slides highlighting the 2018 projects that are from the Storybook program
V.-2 List of full 5 year Parks CIP projects
Eagan Parks 2018 Capital Improvement Projects
https://cityofeagan.maps.arcgis. com/apps/MapJoumal/re sources/tpl/v...
Eagan Parks 2018 Capital
Improvement Projects
This is a printed version of a story map. Dynamic content such as videos and interactive maps is only available in the
online version at htt sp .//arcg is/HOClT
6 73
. 26
73
City of Eagan GIS
71
1 of 15 9/7/2017, 8:52 AM
ji �aR�
*4Kln
@Rion€.
t Pmrk --- --- ,. Lexinaton
I
f.� ------ --
Eagan Parks 2018 Capital Improvement Projects
3of15
1 M
https:Hcityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v...
• Fence has been removed in line with industry standard
• Worked with design team in 2017 for new concrete park specifications and bidding
documents
• Project completion by June 2018
9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects
George
s
https:Hcityofeagan.maps.arcgis.com/apps/MapJoumaYresources/tpl/v ..
Ohmann Park Extension Design & Construction
4 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects
https://cityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpi/v ..
• Removal of a portion of the existing trees on east side of park. Significant tree
clusters and buffers added at about 3:1 ratio
• Expansion of multipurpose fields for soccer, lacrosse and other uses
• Add internal park loop trail connections, including connection to Lebanon Hills
Regional Park on south side
■ Removal of ballfield; movement of existing backstop to west side of park
• Installation of adult fitness pods
■ Removal of horseshoe courts; replace with permanent Cornhole game spaces
GEORGE OHMANN PARK
sa Preliminary Master Plan Concept
P==
61p otkae oW,VIU i o,a�
Ohmann Master Plan
5 of 15 9/7/2017, 8:52 AM
tv
_
sor
1
`ws "1y
777
.
y1 t
•: � �nc�naa i
GEORGE OHMANN PARK
sa Preliminary Master Plan Concept
P==
61p otkae oW,VIU i o,a�
Ohmann Master Plan
5 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects
https:Hcityofeagan.niaps.aregis. com/apps/MapJoumal/resources/tpl/v...
Quarry Park Redesign, pickleball court complex and
pa rki ng
_0V
QUARRY PARK PICKLEBALL IMPROVEMENTS
cot l
Eek: ^li25tla
• Removal of low -use hockey rinks
Eight new pickleball courts, each court individually fenced. Sun shelter commons
area for participants and watching games.
• New parking accommodations (29 additional stalls) for all park users.
• Additional landscape buffers and trail connections
• Construction schedule could be in conjunction with Quarry Road Project
construction for possible cost savings. This construction includes modifications to
existing parking lot, relocating the basketball court and soccer field enhancements.
6 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects https:Hcityofeagan.maps.arcgis.com/apps/MapJoumal/resourees/tpl/v...
7 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects https://cityofeagan.maps.aregis.com/apps/MapJoumal/resources/tpl/v...
Playground Enhancements
+ It has been determined there are no pending full playground replacements needed
for 2018.
* Enhancements include interactive/face-to-face swings and other really cool, unique
play experiences such as Global Motion: a spinning net climber.
Enhancements would be added to existing playgrounds throughout the City.
IN
8 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects
https:Hcityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v...
Asset Management Program Implementation
Thresher Fields Athletic _ Met
3200 Borchert Lane
woorosrrmv Wotton
As part of the overall City Asset Management Plan (AMS), the Park And Recreation
Department will be focusing on the variety of assets within the department for
better budgeting and management.
+ As an example, inventories of underground utilities such as irrigation valves and
piping are needed for pertinent Gopher One Call information or as simple as
9 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects https://cityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v
locating items during repairs.
6 The department identified AMS as a technological tool needed for tracking time
and money in the maintenance of all assets as a high-priority goal.
10 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects https://cityofeagan.maps.arcgis.con /apps/MapJoumal/resources/tpl/v...
• New, free admission amenity for Central Park, located adjacent to the Festival
Pavilion.
■ Splashpad would include toddler zone space, family zone space; all with a
combination of ground sprays, water cannons and vertical elements.
• Included in design will be natural elements for seating, landscape buffers and
shade structures.
Central Park Spray Park option 1
11 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects
https:Hcityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v ..
Sidewinder Waterbug 1
waterbug L
Central Park Splashpad Design Concept
CENTRAE PARI{ SPIASNPAO I 4R� ►d Qf Equ
EASAN. NN NARLH 2017 Design
12 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects https:Hcityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v
13 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects
Small Projects
https://cityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v...
t trt ,Zoe In.
i:w A Blvd F
tai M
Ix
Long
te Lone Oat ,Fld 701h S t TOth at
0
fJ
r: VA
U01 . 11 Jill rfl
lug& Yankee Doodle UPS [wer Grov
Heights
UPS
Eagan N'.
0
it J .311, CD
Ditfley Rd
rating
Plant NSP EKCq I
NICI � Fbhrt
hn
park d I R pafk
cliffRd r CliffRd cr I loth SAW SL
lebnmn Hilh:.
KA
117ffi S,
Vot's-41114 Pkwy.E
> Bumsvffle
.9 ZOO
IRd :R
I
0 McAndrO5'
McAnd—Air, Rd rr
Esri, HERE, Garmin, NGA, USGS, NPS
A p-11. U.It- 140th 3 t W I
14 of 15 9/7/2017, 8:52 AM
Eagan Parks 2018 Capital Improvement Projects https://cityofeagan.maps.arcgis.com/apps/MapJoumal/resources/tpl/v...
Bike racks at remaining sites: (link available only in online story)a continuation of an ongoing objective to
-----------------------------------------------------------------------
install bike racks at park buildings and park destinations
South Oaks Park deck/dock (rebuild salvaged Fish Lake pier): (link available only in online
------------------------------------------------
AOry)refurbish parts of the salvaged Fish Lake pier for a replacement of the deck at South Oaks that was removed in 2017
Radio Controlled Track (RC Course): (link available only in online story)Portions ofthe bike park at Lexington Diffley
---------------------------------------------------------------------------------------------------------------------------------------
Athletic Fields are currently unused. Park staff has been approached by local RC enthusiasts for creating a track for RC usage.
Cedar Pond retaining wall construction: (link available only in online story)rheoldwoodenretainingwallonthe
------------------------- -------------------------------------------------------------------------------------
east side of Cedar Pond is deteriorating. In conjunction with the Public Works Department, construction includes removal of the old wall, repair of inlet pipe and shoreland restoration to match
the other portions of the pond.
Additional tennis boards: (link available only in online story)acontinuationofa2017objectivetoaddthisasapracticeamenity
----------------------------------------------------------------
at our tennis courts. Sites include several on the north portion of the City and south central areas.
10 additional benches along city trails: (link available only in online story)continueaddingbenchesalongtrail
---------------------------- ---------------------------------------------------------------------------------------------------------------
corridors and significant viewing opportunities
15 of 15 9/7/2017, 8:52 AM
2018 Location: total $ Location Equity Contract Lexington Diffley Skate Park (roll over from 2017) $300,000 se high yes George Ohmann Park extension Design and construction $425,000 sw med yes Phase I includes baseball diamond move, expand north MP fields, trail connections/extensions, adult fitness park, bags game area, rain gardens and landscape buffers with approximately 40 new trees planted in park Quarry Park redesign, pickle ball** court complex addition and parking*** $350,000 nw high yes Playground enhancements $50,000 ne and sw med no Asset Management program implementation $50,000 all low yes Splash pad design and construction, including shade structure $410,000 nw med yes Small projects $80,000 *additional tennis boards $3,000 varied low no *10 benches along trails in the city $20,000* varied high yes *Cedar Pond retaining wall reconstruction $15,000 varied med yes *Northview disc golf improvements $25,000 tbd tbd no *bike racks at remaining sites $3,000 varied high no *Radio controlled track (RC course) $3,000 tbd low no * South Oaks Park deck/dock (rebuild salvaged Fish Lake pier) $1,000 se low no Contingency $10,000 Allocation for Public Art $20,000 varied high yes Total for 2018 proposed $1,660,000 Net cost from Park Dedication fund $1,660,000 *will include four additional art benches **grant opportunities available ***additional funding for park modifications out of major street fund
2019 Project: Total $ Location Equity Contract Goat Hill or Trapp Farm Building reconstruction $750,000 se med yes Playground enhancements $50,000 varied med no All Inclusive Playground* $250,000 ytd high yes Nature Trail additional development/expansion $500,000 ne high no Small Projects $80,000 varied med no Allocation for Public Art $20,000 varied high yes Total costs $1,650,000 Total Net cost from Park Dedication Funds $1,650,000 **CDBG Funds available of $30,000 2020 Project: Total $ Location Equity contract Quarry Park Building reconstruction/addition $600,000 nw med yes Rahn Park athletic fields and park development $600,000 sw med yes includes fields, sun shelter/bathroom install, and trail development) Playgrounds (2) $100,000 varied med no Small Projects $80,000 varied med no Allocation for Public Art $20,000 varied high yes Total for 2020 proposed $1,400,000
2021 Rahn building reconstruction $500,000 sw med yes Goat Hill or Trapp Farm Building rebuild $750,000 se med yes Small Projects $80,000 varied high no Playgrounds (2) $100,000 varied high no Allocation for public art $20,000 varied high yes Total for 2021 proposed $1,450,000 2022 Sky Hill Building refurbish $200,000 nw med no Playgrounds (3) $150,000 varied high no Small Projects $100,000 varied high no Allocation for public art $20,000 varied high yes Total for 2022 proposed $470,000
Summary of fund balance position over the life of this 2018 – 2022 CIP budget (estimated) Year beginning balance revenues expenses ending balance 2017 $2,850,000 $1,300,000 $1,165,000 $2,985,000 2018 $2,985,000 $1.400,000 $1,660,000 $2,725,000 2019 $2,725,000 $1,000,000 $1,650,000 $2,075,000 2020 $2,075,000 $750,000 $1,400,000 $1,425,000 2021 $1,425,000 $750,000 $1,450,000 $725,000 2022 $725,000 $750,000 $470,000 $1,005,000 *These projections take in effect what we know at this time, making a few assumptions on growth of tax revenues as tax base increases, and no downturn in the economy. Growth and estimated park dedication fees will be received from several new developments, including the commercial/residential large development that will impact Quarry Park. **Grants will continue to be sought out for on all applicable projects during this 5 year time CIP period.