Loading...
2685 Vikings Cir - E-Sports Training Center Test & Balance Report 2020-01-061046 Fax (763) 657-0587 HVAC TESTING & BALANCING REPORT ESPORT TRAINING CENTER EGAN Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428-1006 Phone (763) 657-0159 Cell (612) 272-5651 Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 Cell: (612) 272-5651 CERTIFIED TEST; ADJUST; BALANCE REPORT # DATE PROJECT ADDRESS ENGINEER HVAC CONTRACTOR NEBB TAB FIRM NEBB TAB SUPERVISOR CERTIFICATION NUMBER 3242 1/6/2020 ESPORT TRAINING CENTER Test & Balance Associates, Inc. Donald J. Henderson MASTER MECHANICAL, INC. (651) 905-1600 ONE (877) 380-0501 2685 VIKINGS CIRCLE SUITE #100 EGAN MN Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 1047 PROJECT ADDRESS THE DATA PRESENTED IN THIS REPORT IS A RECORD OF SYSTEM MEASUREMENTS AND FINAL ADJUSTMENTS THAT HAVE BEEN OBTAINED IN ACCORDANCE WITH THE CURRENT EDITION OF THE NEBB PROCEDURAL STANDARDS FOR TESTING, ADJUSTING, AND BALANCING OF ENVIRONMENTAL SYSTEMS. ANY VARIANCES FROM DESIGN QUANTITIES, WHICH EXCEED NEBB TOLERANCES, ARE NOTED IN THE TEST - ADJUST - BALANCE REPORT PROJECT SUMMARY. SUBMITTED & CERTIFIED BY: NEBB TAB FIRM NEBB TAB SUPERVISOR REG. NO. SIGNATURE DATE CERTIFICATION EXPIRATION DATE CERTIFICATION REPORT 3/31/2020 ESPORT TRAINING CENTER 2685 VIKINGS CIRCLE SUITE #100 EGAN MN 1/6/2020 Test & Balance Associates, Inc. Donald J. Henderson 3242 Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 PROJECT:4879 - ESPORT TRAINING CENTER Project Notes and Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MULTI AIR DISTRIBUTION SYSTEM EXISTING RTU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MULTI AIR DISTRIBUTION SYSTEM EXISTING RTU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MULTI AIR DISTRIBUTION SYSTEM EXISTING RTU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MULTI AIR DISTRIBUTION SYSTEM EXISTING RTU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MULTI AIR DISTRIBUTION SYSTEM EXISTING RTU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MULTI AIR DISTRIBUTION SYSTEM EXISTING EXHAUST. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . FLOW FITTING REPORT SYSTEM EXISTING HEATING WATER. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Instrument Calibration Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Symbol Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Symbol Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Symbol Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Symbol Report. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 TABLE OF CONTENTS 1 2 3 4 6 7 8 9 10 11 12 13 Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 1050 PROJECT:4879 - ESPORT TRAINING CENTER DESCRIPTION:EXECUTIVE SUMARY PROJECT NOTES AND SUMMARY REPORT PAGE:1 of 13 TEST DATE:Jan 2020 THE SCOPE OF THE TESTING AND BALANCING WAWS TO MEASURE AND BALANCE SUPPLY, EXHAUST AND FAN POWERED CFM TO DESIGN VALUES AS LISTED ON THE MECHANICAL DRAWINGS DATED 10/01/2019. THE FANS WERE TESTED UNDER NORMAL OPERATING CONDITIONS IN THE OCCUPIED MODE. 1051 PAGE: 2 of 13 PROJECT: ESPORT TRAINING CENTER DATE: Jan 2020 SYSTEM: EXISTING RTU TECH: BRIAN STOUT DESIGN PRELIMINARY FINAL NO.SIZE FACTOR VEL CFM VEL CFM VEL CFM FPV-1 RECEPTION 1 8 HOOD --250 --264 WAITING 2 8 HOOD --100 --96 WAITING 3 8 HOOD --100 --101 MAXIMUM CFM 8 .349 1289 450 1403 490 1414 493 MINIMUM CFM 8 .349 401 140 406 142 FLOW FACTOR 450 2.24 1.89 FAN CFM 15/13.5 1.406 220 309 236 332 FPV-2 BREAK AREA 1 8 HOOD --150 -- BREAK AREA 2 8 HOOD --150 -- BREAK AREA 3 8 HOOD --150 -- MAXIMUM CFM 8 0.349 1289 450 1485 518 1293 451 MINIMUM CFM 8 0.349 401 140 411 143 FLOW FACTOR 450 2.24 1.67 FAN CFM 15/13.5 1.406 220 309 FPV-3 OPEN AREA 1 16/10 1.111 90 100 91 101 OPEN AREA 2 16/10 1.111 90 100 86 96 OPEN AREA 3 16/10 1.111 90 100 88 98 OPEN AREA 4 16/10 1.111 90 100 93 103 MAXIMUM CFM 8 0.349 1146 400 1158 404 1158 404 MINIMUM CFM 8 0.349 344 120 351 122 FLOW FACTOR 400 2.24 2.20 FAN CFM 15/13.5 1.406 199 280 570 803 198 278 * FAN POWER VAV FANS SHUT OFF WHEN SET TO MAX CFM FPV-2 FAN IS NOT OPERATING AREA SERVED OPENING TEST & BALANCE ASSOCIATES, INC. AIR DISTRIBUTION REPORT 1052 PAGE: 3 of 13 PROJECT: ESPORT TRAINING CENTER DATE: Jan 2020 SYSTEM: EXISTING RTU TECH: BRIAN STOUT DESIGN PRELIMINARY FINAL NO.SIZE FACTOR VEL CFM VEL CFM VEL CFM FPV-4 OPEN AREA 1 16/10 1.111 90 100 110 122 OPEN AREA 2 16/10 1.111 90 100 106 118 MAXIMUM CFM 6 0.196 1020 200 1486 291 1031 202 MINIMUM CFM 6 0.196 408 80 415 81 FLOW FACTOR 200 2.8 1.31 FAN CFM 15/13.5 1.406 120 114 160 VAV-1 OFFICE 1 8 HOOD --150 --149 CORRIDOR 2 8 HOOD --150 --144 MAXIMUM CFM 300 293 MINIMUM CFM 200 198 FLOW FACTOR 2.24 2.33 VAV-2 OPEN AREA 1 8 .349 1433 500 1530 534 1445 504 MAXIMUM CFM 500 504 MINIMUM CFM 8 .349 373 130 579 202 FLOW FACTOR 2.24 1.92 VAV-3 OPEN AREA 1 8 .349 1433 500 1526 533 1455 508 MAXIMUM CFM 500 508 MINIMUM CFM 8 .349 573 200 584 204 FLOW FACTOR 2.24 2.00 AREA SERVED OPENING TEST & BALANCE ASSOCIATES, INC. AIR DISTRIBUTION REPORT 1053 PAGE: 4 of 13 PROJECT: ESPORT TRAINING CENTER DATE: Jan 2020 SYSTEM: EXISTING RTU TECH: BRIAN STOUT DESIGN PRELIMINARY FINAL NO.SIZE FACTOR VEL CFM VEL CFM VEL CFM VAV-4 OPEN AREA 1 12 HOOD --400 --411 OPEN AREA 2 12 HOOD --400 --391 MAXIMUM CFM 8 0.349 2292 800 2423 847 2298 802 MINIMUM CFM 8 0.349 917 320 913 319 FLOW FACTOR 2.24 2.02 VAV-5 OPEN AREA 1 12 HOOD --500 400 --548 OPEN AREA 2 12 HOOD --500 367 --456 MAXIMUM CFM 8 0.349 1000 2876 1004 2876 1004 MINIMUM CFM 8 0.349 400 431 FLOW FACTOR 2.24 1.99 VAV-6 OFFICE 1 10 HOOD 1651 900 1834 1000 1663 906 MAXIMUM CFM 900 906 MINIMUM CFM 240 244 FLOW FACTOR 1.96 1.62 VAV-7 OFFICE 1 8 HOOD --200 --201 MAXIMUM CFM 200 201 MINIMUM CFM 80 84 FLOW FACTOR 2.80 2.8 AREA SERVED OPENING TEST & BALANCE ASSOCIATES, INC. AIR DISTRIBUTION REPORT 1054 PAGE: 5 of 13 PROJECT: ESPORT TRAINING CENTER DATE: Jan 2020 SYSTEM: EXISTING RTU TECH: BRIAN STOUT DESIGN PRELIMINARY FINAL NO.SIZE FACTOR VEL CFM VEL CFM VEL CFM VAV-8 OFFICE 1 6 0.196 2041 400 2264 444 2038 399 MAXIMUM CFM 400 399 MINIMUM CFM 160 164 FLOW FACTOR 2.80 2.29 VAV-9 OFFICE 1 12 HOOD --400 --381 OFFICE 2 8 HOOD --100 --110 OFFICE 3 8 HOOD --100 --106 MAXIMUM CFM 600 597 MINIMUM CFM 240 236 FLOW FACTOR 2.24 2.37 VAV-10 OPEN AREA 1 100 * OFFICE 2 100 STORAGE 3 100 OFFICE 4 100 OFFICE 5 500 MAXIMUM CFM 900 MINIMUM CFM 240 FLOW FACTOR 1.96 AREA SERVED OPENING TEST & BALANCE ASSOCIATES, INC. AIR DISTRIBUTION REPORT 1056 PAGE: 6 of 13 PROJECT: ESPORT TRAINING CENTER DATE: Jan 2020 SYSTEM: EXISTING RTU TECH: BRIAN STOUT DESIGN PRELIMINARY FINAL NO.SIZE FACTOR VEL CFM VEL CFM VEL CFM 1ST FLOOR MENS 1 8 0.349 --150 --161 1ST FLOOR WOMENS 2 8 0.349 --150 --163 AREA SERVED OPENING TEST & BALANCE ASSOCIATES, INC. AIR DISTRIBUTION REPORT 1055 PAGE: 7 of 13 PROJECT: ESPORT TRAINING CENTER DATE: Jan 2020 SYSTEM: EXISTING EXHAUST TECH: BRIAN STOUT DESIGN PRELIMINARY FINAL NO.SIZE FACTOR VEL CFM VEL CFM VEL CFM RESTROOM 1 6 0.196 --70 --29 1ST FLOOR MENS 2 6 0.196 --200 --90 1ST FLOOR WOMENS 3 6 0.196 --200 --92 AREA SERVED OPENING TEST & BALANCE ASSOCIATES, INC. AIR DISTRIBUTION REPORT 1057 UNIT TYPE LOCATION FLOW FITTING SIZE SETTING DESIGN GPM FINAL P.D. FINAL GPM NOTES FPV-1 RECEPTION 3/4 34 1.6 17.2 1.7 FPV-2 BREAK AREA 3/4 48 .9 24.2 .85 FPV-3 OPEN AREA 3/4 38 1.4 21.0 1.5 FPV-4 OPEN AREA 3/4 48 .8 23.2 .84 FTR-1 3/4 .20 NI FTR-2 3/4 1.0 NI FTR-3 3/4 .50 NI NOTE: SYSTEM: EXISTING HEATING WATER DATE: Jan 2020 TEST & BALANCE ASSOCIATES, INC. FLOW FITTING REPORT PROJECT: ESPORT TRAINING CENTER PAGE: 8 of 13 TECHNICIAN: BRIAN STOUT Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 1048 PROJECT:4879 - ESPORT TRAINING CENTER REMARKS: INSTRUMENT CALIBRATION REPORT ADM-880C M8403 MANUFACTURER MODEL SERIAL Shortridge Inst.2/17/2019 APPLICATION AIR PRESSURE/VOLUME Jan 2020 PAGE:9 of 13 CALIBRATION DATE Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 PROJECT:ESPORT TRAINING CENTER SYMBOL DESCRIPTION SYMBOL DESCRIPTION A/C Air Conditioning(er)CLG Ceiling A/AMP Ampere COM Common AC Alternating Current COMP Compressor Unit AD Access Door CONFIG Configuration ADJ Adjustable CONV Convector ADM Airdata Multimeter CP Condenser Pump AF Air Filter/Airfoil CPS Cycles Per Second AFMS Airflow Measuring Station CR Condenser Water Return AHU Air Handling Unit CS Condenser Water Supply ALT Alternate CT Cooling Tower AMB Ambient CUH Cabinet Unit Heater AP Access Panel CWR Chilled Water Return AUTO Automatic CWS Chilled Water Supply BAL Balancing DB Dry Bulb BBR Baseboard Radiation DC Direct Current BC Balancing Cock DDC Direct Digital Control BHP Break Horse Power DEG Degree BI Backward Inclined DH Duct Heater BLDG Building DIA Diameter BRG Bearing DIAG Diagonal BTU British Thermal Unit DIFF Diffuser BTUH BTU Per Hour DISCH Discharge C Condenser Water DISTR Distribution CD Ceiling Diffuser DM Damper Motor CENT Centrifugal DMPR Damper CF Cubic Feet DN Down CFH Cubic Feet Per Hour DPS Diff. Pressure Switch CFM Cubic Feet Per Minute DX Coil Direct Expansion Coil CKT Circuit E East CL Centerline EA Exhaust Air 10 of 13 ABBREVIATIONS PAGE ONE Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 PROJECT:ESPORT TRAINING CENTER SYMBOL DESCRIPTION SYMBOL DESCRIPTION EAT Entering Air Temperature GEN General EDH Electric Duct Heater GF Gas Furnace EF Exhaust Fan GHR Glycol-water Heating Return EFF Efficiency GHS Glycol-water Heating Supply ENT Entering GPH Gallons Per Hour EQUIP Equipment GPM Gallons Per Minute ER Exhaust Register GR Grille ESP External Static Pressure H Height EST Estimate HD Head EWT Entering Water Temperature HOA Hand off Automatic EXH Exhaust HORIZ Horizontal EXIST Existing HP Heat Pump/Horsepower EXT Exterior HR Hour F Fahrenheit/Furnace HT Height FA Fresh Air HTG Heating FC Forward Curved HTR Heater FCU Fan Coil Unit HV Heating Ventilating Unit FD Fire Damper HVAC Heating Ventilating and Air Conditioning FIG Figure HWR Heating Hot Water Return FME Flow Measuring Equipment HWS Heating Hot Water Supply FMS Flow Measuring Station HX Heat Exchanger FPM Feet Per Minute HZ Hertz FPS Feet Per Second ID Inside Diameter FSD Fire/Smoke Damper IH Intake Hood FT Feet (Foot)INT Interior; Internal FTR Finned Tube Radiation IN Inch GA Gauge KH Kitchen Hood GAL Gallon KHE Kitchen Hood Exhaust Fan 11 of 13 ABBREVIATIONS PAGE TWO Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 PROJECT:ESPORT TRAINING CENTER SYMBOL DESCRIPTION SYMBOL DESCRIPTION KHS Kitchen Hood Supply Fan N North KIT Kitchen N/A Not Applicable KV Kilovolt NC Normally Closed KVA Kilovolt Amperes NEMA National Electrical-Manufacturers Assn. KW Kilowatt NIC Not In Contract KWH Kilowatt Hour NO Normally Open/Number LAB Laboratory OA Outside Air LAT Leaving Air Temperature OBD Opposed Blade Damper LB/LBS Pound/Pounds OC On Center LF Linear Foot OD Outside Diameter LIN Linear P/T Pressure/Temp. Test Port LVG Leaving P Pump LWT Leaving Water Temp.PCF Pounds Per Cubic Foot MA Mixed Air PD Pitch Diameter MAN Manual PD Pressure Drop MAU Makeup Air Unit PE Pneumatic Electric MAV Manual Air Vent PF Power Factor MAX Maximum PG Pressure Gage MBH/MBTUH Thousand BTU Per Hour PH Phase MVD Manual Volume Damper PNEU Pneumatic MECH Mechanical PROP Propeller MEZZ Mezzanine PRV Pressure Reducing Valve MHWR Med Temp Heating Water Return PRV Power Roof Ventilation MHWS Med Temp Heating Water Supply PSF Pounds Per Sq. Ft. MIN Minimum PSI Pounds Per Sq. Inch MISC Miscellaneous PSIA Pounds Per Square Inch Absolute 12 of 13 ABBREVIATIONS PAGE THREE Test & Balance Associates, Inc. 7308 Aspen Lane, Suite 110 Brooklyn Park, MN 55428 Phone: (763) 657-0159 Fax: (763) 657-0587 PROJECT:ESPORT TRAINING CENTER SYMBOL DESCRIPTION SYMBOL DESCRIPTION PSIG Pounds Per Square Inch Gauge TEMP Temperature PWR Power TF Transfer Fan RA Return Air TFSP Total Fan Static Pressure RAD or R Radius TONS Tons of Air Conditioning RAT Return Air Temperature TS Temperature Sensor REG Register TSP Total Static Pressure RF Return Fan UH Unit Heater RH Relative Humidity UV Unit Ventilator RH Relief Hood V Volt RHC Reheat Coil VAV Variable Air Volume RPM Revolutions Per Minute VEL Velocity RTU Rooftop Unit VENT Ventilation S Sensor/South VERT Vertical SA Supply Air VFD Variable Frequency Drive SAT Supply Air Temperature VM Voltmeter SD Smoke Damper VOL Volume SENS Sensible VSMC Variable Speed Motor Controller SF Square Foot/Supply Fan W West SP Static Pressure WB Wet Bulb SPL Sound Pressure Level WFMD Water Flow Measuring Device SQ Square WT Weight SUC Suction YD Yard T/T-STAT Thermostat &And TA Transfer Air @ At TB Terminal Box #Number TC Temperature Control + Plus/Positive TD Temperature Differential -Minus/Negative 13 of 13 ABBREVIATIONS PAGE FOUR