EA185654 - Building - Commercial/Industrial - Issued Date 08/24/2023 PERMIT
City of Eagan Permit Type: Building
3830 Pilot Knob Rd Permit Number: EA185654
Eagan, MN 55122
(651)675-5675 EAGAN
www.cityofeagan.com * E A 1 8 5 6 5 4
Date Issued: 8/24/2023
Site Address: 3100 Courthouse Lane
Lot: 3 Block: 2 Addition: Oakview Center
PID:10-53790-02-030
Use: PS Midwest One LLC * 1 0 — 5 3 7 9 0 — 0 Z — 0 3 D
Description:
Sub Type: Commercial/Industrial Construction Type: II-B
Work Type: Solar
Description: 173.9kW Solar Photovoltaic Roof Mounted Array
Census Code: - Occupancy: S-1
Zoning:
Square Feet: 0
Comments:
Fee Summary: BL-Base Fee $1,076.80 0801.4085
Valuation: 86,950.00 BL-Plan Review 65% $699.92 0720.4222
Surcharge-Based on Valuation $43.50 9001 2195
Total: $1,820.22
Contractor: - Applicant - Owner:
MN Solar Ps Mid West One LLC(Public Storage)
11830 Cty Rd 13 SE 701 Western Ave Ste 500
Watertown MN 55388 Glendale CA 91201
(320)444-5694
This permit shall be null and void if work does not start within 180 days of issuance, or if work is suspended for 180 days or more after
started.
I hereby acknowledge that I have read this application and state that the information is correct and agree to comply with all applicable State
of Minnesota Statutes and City of Eagan Ordinances.
Applicant/Permitee: Signature Issued By: Signature
M E C E I V E�pi�,
--------------------------
For Office Use
0 Building Permit#: 185654
S&W Permit#:
EAGAN IPermit Fee: 1X20. 2-21
I Date Received: 8/1/2023
3830 PILOT KNOB ROAD I EAGAN, MN 55122-1810
(651) 675-56751 FAX: (651)675-5694
_cityofeagan.com
Plan Submittal: buildinginspectionsp ——————————————————————————I I Date Issued: I
COMMERCIAL BUILDING PERMIT APPLICATION
Date: 8/1/23 Site Address: 3100 Courthouse Ln, Eagan, MN 55121 Suite#:
Tenant Name: I (AZ Tenant is: El New 2 Existing
Former Tenant(if applicable):
Leah Johnson 320.444.5694
Name: Phone:
Applicant Applicant is: El Owner 0 Contractor El Agent Email: Leah @ mnsolarandmore.com
Type of Description of work: 173.9kW Solar Photovoltaic Roof Mounted Array
Work 86,950
I Construction Cost:
MN Solar Leah Johnson
Company: Contact:
11830 County Rd 13 SE, Watertown, MN 55388
Building Address/City/Zip:
Contractor 320.444.5694 Leah@ mnsolarandmore.com j Kai ICA)
Phone: Email:
License#: BC777439 Expiration Date: 3/31/24
Company: Contact:
Architect/
Engineer Address/City/Zip-,
Phone: Email:
.......... 111___
ewer Company: Contact:
Water
Contractor Address/City/Zip:
Required for Phone: Email:
new construction
and additions
I License#: Expiration Date:
El I understand that Plumbing, Mechanical, Fire Suppression, and Sign work require separate applications.
NOTE: Plans and supporting documents that you submit are considered to be public information. Portions of the information
may be classified as non=�ublic_if ou�rovide specific reasons that would permit the City to conclude that thpy are trade secrets. I
I hereby acknowledge that this information is complete and accurate; that the work will be in conformance with the ordinances and codes of the City of Eagan;
that I understand this is not a permit, but only an application for a permit, and work is not to start without a permit; that the work will be in accordance with the
approved plan in the case of work which requires a review and approval of plans.
Leah Johnson fk4,
Applicant's Printed Name Applicis *nature
FOR OFFICE USE ONLY
SUB TYPES Site Address:lm-I COU,(tbov-fe
Tenant:
Foundation _ Public Facility Antennae VS M)dWaLD 0-
Commercial/Industrial Accessory Building
Apartments _ Greenhouse/Tent Permit#:
WORK TYPES
_ New _ Interior Improvement Demolish Building*
Addition Exterior Improvement Demolish Interior
_ Alteration _ Retaining Wall Demolish Foundation
*Demolition of entire building—give PCA handout to applicant
DESCRIPTION 91
Valuation 0 9S�' Code Edition � MCES System -
Plan Review -X Zoning SAC Units
Census Code "" Stories City Water
#of Units Square Feet Fire Sprinklers
Type of Construction Length
Occupancy T—
p Y S'I Width
REQUIRED INSPECTIONS
Footings_New Building—Addition Retaining Wall
Foundation Foundation Before Backfill Other:
Vapor Barrier Other:
Framing 30 Minutes 1 Hour
Insulation
Sheetrock Final/C.O. Required
Roof:_Decking _Insulation _Ice &Water _Final Final/No C.O. Required
Siding:_Lath _Brick_EFIS
Fireplace:_Rough In _Air Test _Final
Pool:_Footings —Air/Gas Tests _Final
Final C/O Inspection: Schedulec7ire Marshal to be present: Yes - No
New Business to Eagan:
1'
Reviewed By: /: , Building Inspector
FEES
Base Fee fU7t Landscape Guarantee (9001.2257)
Surcharge e Ary3. Tree Mitigation (9111.4677) �--
2
Plan Review Tree Performance Security (9111.2257)
MCES SAC Stormwater Performance Security (6501.2257)
City SAC
S&W Permit& Surcharge --
Treatment Plant
Treatment Plant (Irrigation)
Park Dedication (9328.4670) G-`=—
Trail Dedication (9375.4671) TOTAL: $ 0.00