2020 Cliff Rd - Final Inspection MemosMEMORANDUM.?
TO: ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIHA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAI,
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSOPi, ELECTRICAL IN5PECTOR
MIKE RIDLEY, SENIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans are in our plan review section for your review and comment.
#3
Please return this form to mv attention with your signed comments and the date of review
within seven days. If you have any concerns with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that aze to be collected with the building permit:
AMOUNT
? Yes ? No
landscape security required
water quality dedication
park dedication
trail dedication
ZONING?
METER SIZE
? Yes ? No
? Yes ? No
? Yes ? No
? Yes ? No
? Yes ? No
tree dedicaYion
PRV Required
,11,?
Signature
9 a6 e-e -
Date
CD/FO RMSBLDG W SPiPLAN REVIE W CRAIG N RE V ISED 9- 02
? ww
5?? I) ? ??IP'I
I XI? :? I 4 4 f
1 . ' ? 4Y ?
g r ?1VI EU f? R A-N D4, ??:. 3,
".;
TO: ARNLE ERHART, SUPERINT'ENDENT OF STREETS & EQUIPMENT
BOB KRIIIA, UTILITY CONSTRUCTION IN5PECTOR
DALE WEGLETTNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SENIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DLRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDTTION
The plans are in our plan review section for your review and comment.
3
? l?s ?a.9v
Please return this form to mv attention with your signed comments and the date of review
within seven days. If you have any concerns with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that are to be collected with the building permiY:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
Yes ? No pazk dedication
? Yes ? No trail dedicarion
? Yes A No tree dedication
? Yes ? No PRV Required
Signature
#3
?t.
ZONING?PO
METER SIZE
D.? ze
Date
C?/FORMS/BLDG INSP/PLAN REVIEW CRAIG N REVISED 9- 02
ql?'Id?!',,??w,MEI,M?I,IiO,?Rt1NDU,M ,„,?qJ,lllH""??
TO: ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIAA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOI3N GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SEIVIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans aze in our plan review section for your review and comment.
#3
Please return this form to mv attention with your signed comments and the date of review
within seven days. If you have any concems with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Cv.
Tmy-e? jl?,..s 240i No 0.;2 -SP-S
Indicate any fees that are to be collected with the building permit:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? No pazk dedication
? Yes ? No trail dedication
? Yes ? No tree dedication
? Yes ? No PRV Required
?.??-. ???9'??'?i"/?
'gnature
ZONING?
METER SIZE
!o- 3o-oz
Date
CD/FORMS/BLDG INSP/PLAN REV IEW CRAIC N REVISED 9- 02
. , ?? . ? .,? I..• i?ll?l?ll?[:il
MEMORANbUM
TO: ARNIE ERIIART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIHA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SEPIIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYI{, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans are in our plan review section for your review and comment.
#3
Please return this form to mV attention with your signed comments and the date of review
within seven days. If you have any concems with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that are to be collected with the building permit:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? No park dedication
0 Yes ? No trail dedication
? Yes ? No tree dedication
? Yes ? No PRV Required
Signature
ZONING?
METER SIZE
Date
CD/FORMS/BLDG MSP/PLAN REVIEW CRAIG N ftEVISED 9-02
?It t rs
T ?jll.?t'I
f
?? ?t n u MEMQ$A1N' RM???M,:11,, y
1Yi
a. ?
fi-Op.t--ro:- ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIHA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SENIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
t6 ' -FR61M- CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans are in our plan review section for your review and comment.
?
?
#3
Please return this form to mv attention with your signed comments and the date of review
within seven days. If you have any concerns with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? Npazk dedication
? Yes ? No ?trail dedicafion
? Yes ? N tree dedication
? Yes ? Nd P?RV Required
Signature I
CD/FORMS/BLDG INSP/PLAN R&VIER' CR41G N
ZONING?
METER SIZE
Date
REV ISED 9- 02
Indicate any fees that are to be collected with the building permit:
AMOUNT
, , , ?i , , , ,, , , x , " ni? , ,, "ai , io.
?k OH,M E M'O RA.ND U?M
TO: ARNIE ERHART, SUPERINTENDENT OF ST'REETS & EQUIPMENT
BOB KRIIIA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SEIVIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REV[EW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans are in our plan review section for your review and comment.
#3
Please return this form to mv attention with your signed comments and the date of review
within seven days. If you have any concerns with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Commeuts:
Indicate any fees that are to be collected with the building permit:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? No park dedication
? Yes ? No trail dedication
? Yes ? No tree dedication
? Yes ? No PRV Required
ZONING?
METER SIZE
- 2 ?°G Z--
Sign'ature
Date
CD/FORMS/BLDG INSP/PLAN REVILW CRAIG N REVISED 9- 02
V Q ?n I
MEMORANDUM? ?
TO: ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIHA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
CREGG HOVE, CITY FORESTER
JANIIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SENIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans are in our plan review section for your review and comment.
#3
Please return this form to my attention with your signed comments and the date of review
within seven days. If you have any concerns with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that are to be"collected with the building permit:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? No park dedication
? Yes ? No trail dedication
? Yes ? No tree dedication
? Yes ? No PRV Required
Signature
CD/FORMSBLDG INSV/PCAN RBVIEW CRAIG N
ZONING?
METER SIZE
Date
REVLSED 9-02
TO: ABNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIHA, UTILITY CONSTRIICTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, A55ISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SENIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DIRECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD-HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDTTION
The plans are in our plan review section for your review and comment.
#3
Please return this form to mv attention with your signed comments and the date of review
within seven days. If you have any concerns with these plans, please so indicate on tlus form and
notify and resolve these issues with Yhe affected parties. If you are requesring that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that are to be collected with the building permit:
AMOUNT
? Yes No landscape security required
? Yes ? No water quality dedication
? Yes ? No park dedication
? Yes ? No trail dedication
? Yes ? No tree dedicarion
? s ? No PRV Required
Signa e
CD/FORMS/BLDG INSP/PLAN REVIEW CRAIC N
ZONING?
METER SIZE
Date ?
REVISED 9- 02
TO: ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
BOB KRIHA, UTILITY CONSTRUCTION INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
ERIC MACBETH, WATER RESOURCES COORDINATOR
GREGG HOVE, CITY FORESTER
JAMIE VERBRUGGE, ASSISTANT CITY ADMINISTRATOR
JOHN GORDER, ASSISTANT CITY ENGINEER
KENT THERKELSEN, CHIEF OF POLICE
MARK ANDERSON, ELECTRICAL INSPECTOR
MIKE RIDLEY, SENIOR PLANNER
PAUL HEUER, SYSTEMS ANALYST
SCOTT PETERSON, BUILDING INSPECTOR
TOM COLBERT, DII2ECTOR OF PUBLIC WORKS
TOM PEPPER, CHIEF FINANCIAL OFFICER
FROM: CRAIG NOVACZYI{, SENIOR INSPECTOR '
DATE: SEPTEMBER 25, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK II
LOT 2, BLOCK 1, HADLER PARK ADDITION
The plans are in our plan review section for your review and comment.
#3
Please return this form to mv atfenfiou with your signed conunents and the date of review
within seven days. If you have any concerns with these plans, please so indicate on this form and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building perrrtit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that are to be collected with the building permit:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? No park dedication
? Yes ? No trail dedication
? Yes -;5 No tree dedication
? Yes ? lYq PRV Required
sigr,acure
ZONING?_
METER SIZE
OC,- a -o2-
Date
REVIBWCRAIGN e' ? REVISED9-02
?. ,
city of eagan
MEMO
TO: DALE SCHOEPPNER, CHIEF BUILDING OFFICIAL
DALE WEGLEITNER, FIRE MARSHAL
PAUL OLSON, SUPERINTENDENT OF PARKS
MIKE RIDLEY, SENIOR PLANNER
CAROL TUMINI, UTILITY BILLIPIG CLERK
BOB KRIIiA, CONSTRUCTION INSPECTOR
STAN LEXVOLD, CONSTRUCTION SUPERVISOR
TOM COLBERT, PUBLIC WORKS DIRECTOR
JOHN GORDER, DEVELOPMENT/DESIGN ENGINEER
ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
PAUL HEUER, SYSTEMS ANALYST
ERIC MACBETH, WATER RESOURCE COORDINATOR
MARK ANDERSON, ELECTRICAL INSPECTOR
SCOTT PETERSON, PLUMBING INSPECTOR
FROM: TERRY ZELENKA, COMBINATION INSPECTOR
DATE: JANUARY 22, 2003
SUBJECT: FINAL INSPECTION FOR HOLLYWOOD VIDEO
2020 CLIFF ROAD
LEGAL: LOT 2 BLOCK 1 HADLER PARK
The Protective Inspections Division will be performing a final inspection at 2020 Cliff
Road on Friday, February 21, 2003.
If you are requesting that the Certificate of Occupancy be held, please fill out the proper
hold request form. Failure to return the hold request form will be considered your approval. The
person, or deparhnent, requesting the hold is responsible for notifying and resolving any
problems with the affected parties.
CD/bldg msp/misc/final insp - comm bidgs
city of eagan MEMO
4t3-1
TO: DALE SCHOEPPNER, CHIEF BUILDING OFFICIAL
DALE WEGLEITNER, FIRE MARSHAL
PAUL OLSON, SUPERINTENDENT OF PARKS
MIKE RIDLEY, SENIOR PLANNER
CAROL TUMINI, UTILITY BILLING CLERK
BOB KRIHA, CONSTRUCTION INSPECTOR
STAN LEXVOLD, CONSTRUCTION SUPERVISOR
TOM COLBERT, PUBLIC WORKS DIRECTOR
JOHN GORDER, DEVELOPMENT/DESIGN ENGINEER
ARNIE ERHART, SUPERINTENDENT OF STREETS & EQUIPMENT
PAUL HEUER, SYSTEMS ANALYST
ERIC MACBETH, WATER RESOURCE COORDINATOR
MARK ANDERSON, ELECTRICAL INSPECTOR
SCOTT PETERSON, PLUMBING INSPECTOR
FROM: TERRY ZELENKA, COMBINATION INSPECTOR
DATE: JANUARY 22, 2003
SUBJECT: F1NAL INSPECTION FOR HOLLYWOOD VIDEO
2020 CLIFF ROAD
LEGAL: LOT 2 BLOCK 1 HADLER PARK
The ProtecTive Inspections Division will be performing a final inspection at 2020 Cliff
Road on Friday, February 21, 2003.
If you are requesting that the Certificate of Occupancy be held, please fill out the proper
hold request forxn. Failure to return the hold request form will be considered your approval. The
person, or department, requesting the hold is responsible for notifying and resolving any
problems with the affected parties.
CD/bldg msp/misc/final insp - comm bldgs
MEMORANDUM
TO: KENT THERKELSEN,CHIEF OFPOLICE
TOM PEPPER, CHIEF FINANCIAL OFFICER
JAMIE VERBRUGGE, ASSISTANT CITY ADNIINISTRATOR
MARK ANDERSON, ELECTRICAL INSPECTOR
DALE WEGLEITNER, FIRE MARSHAL
SCOTT PETERSON, PLUMBING INSPECTOR
MIKE RIDLEY, SE1vIOR PLANNER
GREGG HOVE, SUPERVISOR OF FORESTRY
ERIC MACBETH, WATER RESOURCES
ARNIE ERHART, SUPERINTENDENT OF STREETS AND EQUIPMENT
PAUL HEUER, SYSTEMS ANALYST
BOB KRIHA, CONSTRUCTION INSPECTOR
TOM COLBERT, PUBLIC WORKS DIRECTOR
JOHN GORDER, DEVELOPMENT/DESIGN ENGINEER
FROM: CRAIG NOVACZYK, SENIOR INSPECTOR
DATE: JITNE 5, 2002
RE: PLAN REVIEW - 2020 CLIFF ROAD - HADLER PARK
(LOT l, BLOCK 1, HADLER PARK)
The plans are in our plan review section for your review and comment.
#25
Please return this form to mY attention with your signed comments and tlte date of review
within seven days. If you have any concerns with these plans, please so indicate on this forrrt and
notify and resolve these issues with the affected parties. If you are requesting that issuance of the
building permit be held, please fill out the proper "hold" request form.
Comments:
Indicate any fees that are to be collected with the building permit:
AMOUNT
? Yes ? No landscape security required
? Yes ? No water quality dedication
? Yes ? No park dedication
? Yes ? No trail dedication
? Yes ? No tree dedication
? Yes ? No PRV Required
ZONING?
METER SIZE
Signature Date
CD/FORMS/PLAN REVIBW CAAIC N UPDATED 4-6-01